4908 N PLACIDIA AVE 91601

Certificate Information: 4908 N PLACIDIA AVE 91601

Application / Permit
21014-20000-01736
Plan Check / Job No.
B21VN04163
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ECPC:116 SQ. FT. ADDITION TO AND CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/3/2021
Issuing Office
Current Status
CofO Issued on 7/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 COLIN LOREDO
Corrections Issued 4/17/2021 COLIN LOREDO
Applicant returned to address corrections 8/3/2021 COLIN LOREDO
Plan Check Approved 8/3/2021 COLIN LOREDO
Issued 8/3/2021 APPLICANT
CofO in Progress 7/15/2022 JOHN HAYES
Permit Finaled 7/30/2022 DEROLD HAUFF
CofO Issued 7/30/2022 DEROLD HAUFF
Permit Finaled 7/30/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/4/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/5/2021 GABRIEL ROBLES
Sewer availability Cleared 5/5/2021 GABRIEL ROBLES
Construction near power lines Cleared 7/28/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Kazemi,, Milad; Lic. No.: C92143 6250 CANOGA AVE #525      WOODLAND HILLS, CA 91367

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/14/2021 Approved DANIEL DREW
Excavation/Setback/Form/Re-Bar 9/21/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 9/21/2021 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/14/2021 Partial Approval DANIEL DREW
Wood Frame 10/14/2021 Not Ready for Inspection DANIEL DREW
ELECTRICAL-Rough 12/14/2021 Not Ready for Inspection MISAEL ESPARZA
Gas Test 12/14/2021 Corrections Issued MISAEL ESPARZA
HVAC-Rough 12/14/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 12/14/2021 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 12/22/2021 Not Ready for Inspection MATT KELLERMAN
ELECTRICAL-Rough 12/22/2021 Approved MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 12/22/2021 Not Ready for Inspection MATT KELLERMAN
Gas Test 12/22/2021 Approved MATT KELLERMAN
Green Building Rough 12/22/2021 Corrections Issued MATT KELLERMAN
HVAC-Rough 12/22/2021 Not Ready for Inspection MATT KELLERMAN
Interior/Exterior Lathing 12/22/2021 Not Ready for Inspection MATT KELLERMAN
PLUMBING-Rough 12/22/2021 Approved MATT KELLERMAN
BUILDING-Rough-Frame 1/7/2022 Corrections Issued CALEB MEISTER
ELECTRICAL-Rough 1/7/2022 Corrections Issued CALEB MEISTER
Green Building Rough 1/7/2022 Not Ready for Inspection CALEB MEISTER
HVAC-Rough 1/7/2022 Corrections Issued CALEB MEISTER
PLUMBING-Rough 1/7/2022 Approved CALEB MEISTER
BUILDING-Rough-Frame 3/8/2022 Partial Approval DAVID MATSON
ELECTRICAL-Rough 3/8/2022 Corrections Issued DAVID MATSON
Green Building Rough 3/8/2022 Not Ready for Inspection DAVID MATSON
Rough-Elec/Plmb/HVAC 3/8/2022 Corrections Issued DAVID MATSON
Shower Pan 3/8/2022 Approved DAVID MATSON
BUILDING-Rough-Frame 3/15/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 3/15/2022 Approved ARAM AVEDISIAN
Green Building Rough 3/15/2022 Approved ARAM AVEDISIAN
Insulation 3/15/2022 Corrections Issued ARAM AVEDISIAN
Interior/Exterior Lathing 3/15/2022 Approved ARAM AVEDISIAN
Shower Pan 3/15/2022 Approved ARAM AVEDISIAN
Drywall Nailing 3/30/2022 Approved CALEB MEISTER
Insulation 3/30/2022 Approved CALEB MEISTER
ELECTRICAL-Final 6/24/2022 Not Ready for Inspection JOHN HAYES
Final 6/24/2022 Corrections Issued JOHN HAYES
Green Building Final 6/24/2022 Not Ready for Inspection JOHN HAYES
HVAC-Final 6/24/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 6/24/2022 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 6/24/2022 SGSOV Not Ready JOHN HAYES
Smoke Detectors 6/24/2022 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 7/7/2022 Approved JOHN HAYES
Final 7/7/2022 Corrections Issued JOHN HAYES
Green Building Final 7/7/2022 Not Ready for Inspection JOHN HAYES
HVAC-Final 7/7/2022 Approved JOHN HAYES
PLUMBING-Final 7/7/2022 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 7/7/2022 SGSOV Approved JOHN HAYES
Smoke Detectors 7/7/2022 Approved JOHN HAYES
Final 7/14/2022 OK to Issue CofO JOHN HAYES
Green Building Final 7/14/2022 Approved JOHN HAYES