12659 W WELBY WAY 91606

Certificate Information: 12659 W WELBY WAY 91606

Application / Permit
21014-20000-01726
Plan Check / Job No.
B21VN04145
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
330 SQ. FT. ADDITION, W/INTERIOR REMODEL NEW BEDROOM, TWO BATHROOMS AND A LAUNDRY AREA. AND REMOVE SHED/CONCRETE PAVING
Permit Issued
Issued on 12/19/2021
Issuing Office
Current Status
CofO Issued on 4/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 PETER MOSESIAN
Corrections Issued 4/17/2021 PETER MOSESIAN
Plan Check Approved 11/3/2021 PETER MOSESIAN
Issued 12/19/2021 APPLICANT
CofO in Progress 3/3/2023 KIRK SANDERS
Permit Finaled 4/20/2023 MICHAEL SMITH
CofO Issued 4/20/2023 MICHAEL SMITH
Permit Finaled 4/20/2023 MICHAEL SMITH

Permit Application Clearance Information

Sewer availability Cleared 6/24/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/28/2021 ADRIAN CASTRO
Hydrant and Access approval Cleared 8/26/2021 JOHN CONNEALLY
Low Impact Development Cleared 10/27/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/11/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Dream Home Remodeling Inc; Lic. No.: 792977-B 22311 VENTURA BLVD SUITE 110      WOODLAND HILLS, CA 91364
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/5/2022 Conditional Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 1/18/2022 Corrections Issued MICHAEL TEMPLE
Green Building Rough 1/18/2022 Not Ready for Inspection MICHAEL TEMPLE
PLUMBING-Rough 1/18/2022 Not Ready for Inspection MICHAEL TEMPLE
PLUMBING-Rough 1/21/2022 Partial Approval JACK KARGODORIAN
Wood Frame 1/21/2022 Corrections Issued JACK KARGODORIAN
Insulation 1/24/2022 Not Ready for Inspection DEANDRE HOFFMAN
BUILDING-Rough-Frame 1/26/2022 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 1/26/2022 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 1/28/2022 Partial Approval CHRISTOPHER DELLEFIELD
Green Building Rough 1/28/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Insulation 1/28/2022 Partial Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 2/24/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 2/24/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 2/24/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 2/24/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 2/24/2022 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 3/2/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 3/2/2022 Partial Approval CHRISTOPHE COCHRAN
Insulation 3/7/2022 Approved ASHLEY THOMPSON
Shower Pan 3/7/2022 Approved ASHLEY THOMPSON
Drywall Nailing 3/11/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 3/21/2022 Approved CHRISTOPHE COCHRAN
Final 9/19/2022 Not Ready for Inspection RAFAEL CORTES
Footing/Foundation/Slab 9/19/2022 Approved RAFAEL CORTES
Green Building Final 9/19/2022 Corrections Issued RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 9/19/2022 SGSOV Approved RAFAEL CORTES
Smoke Detectors 9/19/2022 Approved RAFAEL CORTES
Final 3/2/2023 OK to Issue CofO KIRK SANDERS
Green Building Final 3/2/2023 Approved KIRK SANDERS