12630 W MIRANDA ST 1-3 91607
Certificate Information: 12630 W MIRANDA ST 1-3 91607
- Application / Permit
- 21014-20000-01705
- Plan Check / Job No.
- B21VN04104
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION & ALTERATION TO (E) SINGLE FAMILY DWELLING: ADD COVERED FRONT PORCH, CONVERT (E) 2-CAR GARAGE TO ACCESSORY DWELLING UNIT, & CONVERT PORTION OF (E) SINGLE FAMILY DWELLING TO JR. ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/1/2021
- Issuing Office
- Current Status
- CofO Issued on 5/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | COLIN LOREDO |
| Corrections Issued | 5/18/2021 | COLIN LOREDO |
| Quality Review Completed | 6/1/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 6/2/2021 | APPLICANT |
| Plan Check Approved | 6/29/2021 | COLIN LOREDO |
| Issued | 7/1/2021 | APPLICANT |
| CofO in Progress | 5/9/2022 | CHRISTOPHE COCHRAN |
| CofO Issued | 5/21/2022 | MICHAEL SMITH |
| Permit Finaled | 5/21/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/21/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 5/21/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/21/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2021 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 5/24/2021 | STEVEN WECHSLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/28/2021 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/9/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 9/22/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 9/22/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Rough | 9/22/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 9/22/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/22/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 9/27/2021 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 9/27/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 9/27/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Wood Frame | 9/27/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Rough | 10/20/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 10/20/2021 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 10/20/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Wood Frame | 10/29/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/12/2021 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 11/12/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 11/12/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 11/18/2021 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 11/23/2021 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 12/10/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 12/22/2021 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 4/12/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 4/12/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 4/12/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Final | 4/12/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 4/12/2022 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 4/12/2022 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 4/12/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 5/2/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 5/2/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 5/9/2022 | OK to Issue CofO | CHRISTOPHE COCHRAN |