8007 W GROVE ST 91040

Certificate Information: 8007 W GROVE ST 91040

Application / Permit
21014-20000-01698
Plan Check / Job No.
B21VN04091
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 28' 11" X 19' 7" IRR.-SHAPE TO (E) DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 9/13/2021
Issuing Office
Valley
Current Status
CofO Issued on 8/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/7/2021 APPLICANT
Assigned to Plan Check Engineer 4/13/2021 GURUNATH NESARAJAH
Corrections Issued 4/13/2021 GURUNATH NESARAJAH
Plan Check Approved 8/30/2021 GURUNATH NESARAJAH
Building Plans Picked Up 8/31/2021 APPLICANT
Issued 9/13/2021 APPLICANT
CofO in Progress 8/3/2022 MATTHEW NELSON
CofO Issued 8/30/2022 MICHAEL SMITH
Permit Finaled 8/30/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/26/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 5/26/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 5/26/2021 DAGOVERTO GUERRERO
ZI Cleared 5/26/2021 DANG NGUYEN
Construction near power lines Cleared 7/13/2021 RIDWAN HARDY
Construction within easement Cleared 7/13/2021 RIDWAN HARDY
Grading Pre-Inspection Cleared 7/22/2021 BRIAN MILLER
Roof/Waste drainage to street Cleared 8/24/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/19/2021 Partial Approval MATTHEW NELSON
Deputy Drilled-In Anchors 11/23/2021 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 11/30/2021 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 1/25/2022 Approved MATTHEW NELSON
ELECTRICAL-Rough 3/3/2022 Approved MATTHEW NELSON
HVAC-Rough 3/3/2022 Approved MATTHEW NELSON
PLUMBING-Rough 3/3/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 3/11/2022 Approved GREGG CUMMINGS
Green Building Rough 3/11/2022 Approved GREGG CUMMINGS
Interior/Exterior Lathing 3/11/2022 Conditional Approval GREGG CUMMINGS
Sewer 3/11/2022 Approved GREGG CUMMINGS
Underground Mechanical 3/11/2022 Approved GREGG CUMMINGS
Wood Frame 3/14/2022 Approved MATTHEW NELSON
Insulation 3/21/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 3/21/2022 Approved MATTHEW NELSON
Drywall Nailing 3/30/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 5/6/2022 Approved MATTHEW NELSON
Final 6/15/2022 Corrections Issued MATTHEW NELSON
Green Building Final 6/15/2022 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 6/15/2022 SGSOV Approved MATTHEW NELSON
Smoke Detectors 6/15/2022 Approved MATTHEW NELSON
Final 6/29/2022 Corrections Issued MATTHEW NELSON
Green Building Final 6/29/2022 Approved MATTHEW NELSON
Final 7/6/2022 Not Ready for Inspection MATTHEW NELSON
Final 8/2/2022 OK to Issue CofO MATTHEW NELSON