5038 N ENFIELD AVE 91316

Certificate Information: 5038 N ENFIELD AVE 91316

Application / Permit
21014-20000-01683
Plan Check / Job No.
B21VN04059
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD ( 17'-10"x 20'-1") TO AND CONVERT THE (E) DET. GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852. 2 (e) (1) (B). WORK PER ENGINEER.
Permit Issued
Issued on 5/14/2021
Issuing Office
Current Status
CofO Issued on 8/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2021 APPLICANT
Assigned to Plan Check Engineer 4/12/2021 TROY DEGUZMAN
Corrections Issued 4/12/2021 TROY DEGUZMAN
Plan Check Approved 5/14/2021 TROY DEGUZMAN
Issued 5/14/2021 APPLICANT
CofO in Progress 6/22/2023 SEAN HAUPT
Permit Finaled 8/30/2023 JOHN JANSON
CofO Issued 8/30/2023 JOHN JANSON
Permit Finaled 8/30/2023 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 4/19/2021 WALTER RAMIREZ
Address approval Cleared 4/20/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 4/21/2021 GABRIEL ROBLES
Sewer availability Cleared 4/21/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 4/28/2021 GABRIEL ROBLES
Grading Pre-Inspection Cleared 5/14/2021 TROY DEGUZMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/24/2021 Corrections Issued RYAN SALAZAR
Pre-Inspection 6/24/2021 Partial Inspection STEPHANIE SWANSON
Deputy Drilled-In Anchors 7/6/2021 Conditional Approval RYAN SALAZAR
Footing/Foundation/Slab 7/7/2021 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 7/13/2021 Not Ready for Inspection PETER FOLLING
Footing/Foundation/Slab 7/20/2021 Approved DAVID SANDOVAL
Underground Mechanical 7/20/2021 Partial Approval DAVID SANDOVAL
Deputy Drilled-In Anchors 8/19/2021 Partial Approval DAVID SANDOVAL
Footing/Foundation/Slab 9/14/2021 Approved DAVID SANDOVAL
ELECTRICAL-Rough 10/15/2021 Not Ready for Inspection DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 10/15/2021 Approved DAVID SANDOVAL
PLUMBING-Rough 10/15/2021 Corrections Issued DAVID SANDOVAL
ELECTRICAL-Rough 10/28/2021 Corrections Issued DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 10/28/2021 Approved DAVID SANDOVAL
Green Building Rough 10/28/2021 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 11/4/2021 Approved JAVIER RAMOS JR
Green Building Rough 11/4/2021 Approved JAVIER RAMOS JR
Insulation 11/4/2021 Partial Approval JAVIER RAMOS JR
Interior/Exterior Lathing 11/4/2021 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 11/4/2021 Approved JAVIER RAMOS JR
Drywall Nailing 11/24/2021 Approved DAVID SANDOVAL
Pre-Inspection 2/14/2022 Approved DAVID SANDOVAL
Final 3/3/2022 Corrections Issued DAVID SANDOVAL
Green Building Final 3/3/2022 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 3/3/2022 SGSOV Not Ready DAVID SANDOVAL
Smoke Detectors 3/3/2022 Not Ready for Inspection DAVID SANDOVAL
Final 3/16/2022 Corrections Issued DAVID SANDOVAL
Green Building Final 3/16/2022 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 3/16/2022 SGSOV Not Ready DAVID SANDOVAL
Smoke Detectors 3/16/2022 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 3/30/2022 SGSOV Not Ready DAVID SANDOVAL
ELECTRICAL-Final 4/15/2022 Approved DAVID SANDOVAL
Final 4/15/2022 Partial Approval DAVID SANDOVAL
Green Building Final 4/15/2022 Approved DAVID SANDOVAL
HVAC-Final 4/15/2022 Approved DAVID SANDOVAL
PLUMBING-Final 4/15/2022 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 4/15/2022 SGSOV Approved DAVID SANDOVAL
ELECTRICAL-Final 2/8/2023 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Final 6/15/2023 Corrections Issued JOHN KIDWELL
Final 6/21/2023 OK to Issue CofO SEAN HAUPT