5038 N ENFIELD AVE 91316
Certificate Information: 5038 N ENFIELD AVE 91316
- Application / Permit
- 21014-20000-01683
- Plan Check / Job No.
- B21VN04059
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD ( 17'-10"x 20'-1") TO AND CONVERT THE (E) DET. GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852. 2 (e) (1) (B). WORK PER ENGINEER.
- Permit Issued
- Issued on 5/14/2021
- Issuing Office
- Current Status
- CofO Issued on 8/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/12/2021 | TROY DEGUZMAN |
| Corrections Issued | 4/12/2021 | TROY DEGUZMAN |
| Plan Check Approved | 5/14/2021 | TROY DEGUZMAN |
| Issued | 5/14/2021 | APPLICANT |
| CofO in Progress | 6/22/2023 | SEAN HAUPT |
| Permit Finaled | 8/30/2023 | JOHN JANSON |
| CofO Issued | 8/30/2023 | JOHN JANSON |
| Permit Finaled | 8/30/2023 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/19/2021 | WALTER RAMIREZ |
| Address approval | Cleared | 4/20/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 4/21/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 4/28/2021 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 5/14/2021 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/24/2021 | Corrections Issued | RYAN SALAZAR |
| Pre-Inspection | 6/24/2021 | Partial Inspection | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 7/6/2021 | Conditional Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 7/7/2021 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 7/13/2021 | Not Ready for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 7/20/2021 | Approved | DAVID SANDOVAL |
| Underground Mechanical | 7/20/2021 | Partial Approval | DAVID SANDOVAL |
| Deputy Drilled-In Anchors | 8/19/2021 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 9/14/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 10/15/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2021 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 10/15/2021 | Corrections Issued | DAVID SANDOVAL |
| ELECTRICAL-Rough | 10/28/2021 | Corrections Issued | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2021 | Approved | DAVID SANDOVAL |
| Green Building Rough | 10/28/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 11/4/2021 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 11/4/2021 | Approved | JAVIER RAMOS JR |
| Insulation | 11/4/2021 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 11/4/2021 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 11/4/2021 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 11/24/2021 | Approved | DAVID SANDOVAL |
| Pre-Inspection | 2/14/2022 | Approved | DAVID SANDOVAL |
| Final | 3/3/2022 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 3/3/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 3/3/2022 | SGSOV Not Ready | DAVID SANDOVAL |
| Smoke Detectors | 3/3/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 3/16/2022 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 3/16/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 3/16/2022 | SGSOV Not Ready | DAVID SANDOVAL |
| Smoke Detectors | 3/16/2022 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 3/30/2022 | SGSOV Not Ready | DAVID SANDOVAL |
| ELECTRICAL-Final | 4/15/2022 | Approved | DAVID SANDOVAL |
| Final | 4/15/2022 | Partial Approval | DAVID SANDOVAL |
| Green Building Final | 4/15/2022 | Approved | DAVID SANDOVAL |
| HVAC-Final | 4/15/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Final | 4/15/2022 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 4/15/2022 | SGSOV Approved | DAVID SANDOVAL |
| ELECTRICAL-Final | 2/8/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Final | 6/15/2023 | Corrections Issued | JOHN KIDWELL |
| Final | 6/21/2023 | OK to Issue CofO | SEAN HAUPT |