11595 W MORRISON ST 91601
Certificate Information: 11595 W MORRISON ST 91601
- Application / Permit
- 21014-20000-01677
- Plan Check / Job No.
- B21VN04043
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) IRREGULAR SHAPED 23' - 3" X 22'-5" ADDITION TO CONNECT (E) GARAGE TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/15/2021
- Issuing Office
- Current Status
- CofO Issued on 8/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2021 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 4/13/2021 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 4/20/2021 | APPLICANT |
| Applicant returned to address corrections | 8/11/2021 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 8/15/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 11/15/2021 | APPLICANT |
| CofO in Progress | 6/30/2022 | THOMAS FINNILA |
| CofO in Progress | 6/30/2022 | THOMAS FINNILA |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
| CofO Issued | 8/25/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/22/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2021 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 5/11/2021 | ADRIAN CASTRO |
| Specific Plan | Cleared | 7/12/2021 | CORREY KITCHENS |
| ZI | Cleared | 7/12/2021 | CORREY KITCHENS |
| ZI | Cleared | 7/12/2021 | CORREY KITCHENS |
Contact Information
| Contractor | All Construction Services; Lic. No.: 1056091-B | 9018 BALBOA BLVD #509 NORTHRIDGE, CA 91325 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22121 CLARENDON ST APT 340 WOODLAND HILLS, CA 91367 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/19/2021 | Approved | THOMAS FINNILA |
| Gas Test | 11/24/2021 | Approved | THOMAS FINNILA |
| Footing/Foundation/Slab | 12/20/2021 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 1/25/2022 | Partial Approval | CALEB MEISTER |
| Green Building Rough | 1/25/2022 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 1/31/2022 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/25/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 2/25/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 2/25/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 2/25/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 2/25/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 3/3/2022 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 3/3/2022 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/3/2022 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 3/8/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/8/2022 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 3/8/2022 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 3/10/2022 | Approved | RYAN SALAZAR |
| Insulation | 3/10/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 3/15/2022 | Approved | CALEB MEISTER |
| Green Building Rough | 3/15/2022 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 5/24/2022 | Approved | MATT KELLERMAN |
| Final | 5/24/2022 | Corrections Issued | MATT KELLERMAN |
| Footing/Foundation/Slab | 5/24/2022 | Approved | MATT KELLERMAN |
| Green Building Final | 5/24/2022 | Approved | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 5/24/2022 | SGSOV Approved | MATT KELLERMAN |
| Smoke Detectors | 5/24/2022 | Approved | MATT KELLERMAN |
| Pre-Inspection | 6/7/2022 | Partial Inspection | ARAM AVEDISIAN |
| Final | 6/24/2022 | OK to Issue CofO | THOMAS FINNILA |