8441 N GLENCREST DR 91352
Certificate Information: 8441 N GLENCREST DR 91352
- Application / Permit
- 21014-20000-01663
- Plan Check / Job No.
- B21VN04004
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE WITH 2-STORY ADDITION FOR AN ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 3/4/2022
- Issuing Office
- Current Status
- Issued on 3/4/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2021 | COLIN LOREDO |
| Corrections Issued | 5/11/2021 | COLIN LOREDO |
| Quality Review Completed | 5/24/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 5/27/2021 | APPLICANT |
| Plan Check Approved | 2/23/2022 | COLIN LOREDO |
| Issued | 3/4/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/13/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/15/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 11/8/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 11/18/2021 | TA ANH |
| Hydrant and Access approval | Cleared | 2/3/2022 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 2/7/2022 | ABDULLAH SADOZAI |
| Grading Pre-Inspection | Cleared | 2/23/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/25/2023 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 5/3/2023 | Approved | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 5/9/2023 | Conditional Approval | MICHAEL SMITH |
| Excavation/Setback/Form/Re-Bar | 5/9/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 5/16/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 5/22/2023 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2023 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2023 | Partial Approval | DAVID ANDERSON |
| Special/Order Compliance | 6/29/2023 | Corrections Issued | DAVID ANDERSON |
| Deputy Wood Construction | 7/14/2023 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 9/18/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 9/18/2023 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 9/18/2023 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 9/19/2023 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Rough | 9/19/2023 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 9/19/2023 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/21/2023 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 9/21/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | Partial Approval | DAVID ANDERSON |
| Green Building Rough | 9/21/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 9/21/2023 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 9/21/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 9/21/2023 | Approved | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 9/21/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/26/2023 | Approved | DAVID ANDERSON |
| Wood Frame | 9/26/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 10/12/2023 | Approved | DAVID ANDERSON |
| Insulation | 10/18/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 10/24/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 11/1/2023 | Corrections Issued | DAVID ANDERSON |
| Shower Pan | 11/6/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 12/27/2023 | Partial Approval | DAVID ANDERSON |
| Interior/Exterior Lathing | 1/8/2024 | Approved | DAVID ANDERSON |
| Underground Mechanical | 4/29/2024 | Approved | DAVID ANDERSON |
| Sewer | 5/14/2024 | Approved | DAVID ANDERSON |
| Final | 10/15/2025 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 10/15/2025 | Approved | DAVID ANDERSON |
| Green Building Final | 10/15/2025 | Approved | DAVID ANDERSON |
| MERV13>=Final | 10/15/2025 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 10/15/2025 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 10/15/2025 | Approved | DAVID ANDERSON |