8222 N LINDLEY AVE 91335

Certificate Information: 8222 N LINDLEY AVE 91335

Application / Permit
21014-20000-01638
Plan Check / Job No.
B21VN03916
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 14' 6" X 26' TO DETACHED REC ROOM/STORAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 3/10/2022
Issuing Office
Current Status
CofO Issued on 9/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2021 APPLICANT
Assigned to Plan Check Engineer 4/8/2021 GURUNATH NESARAJAH
Corrections Issued 4/11/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 12/7/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 1/22/2022 GURUNATH NESARAJAH
Plan Check Approved 3/1/2022 GURUNATH NESARAJAH
Building Plans Picked Up 3/1/2022 APPLICANT
Issued 3/10/2022 APPLICANT
CofO in Progress 8/30/2022 JEFFREY BULL
CofO Issued 9/10/2022 MICHAEL SMITH
Permit Finaled 9/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/21/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 4/21/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 4/26/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 4/26/2021 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 11/9/2021 WALTER RAMIREZ

Contact Information

Contractor M S T Contractors Corporation; Lic. No.: 754023-B 18035 BURTON STREET      RESEDA, CA 91335
Engineer Lee,, Richard C C; Lic. No.: S1371 19321 VANOWEN ST      RESEDA, CA 91335

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/7/2022 Conditional Approval JUSTIN HAWLEY
Excavation/Setback/Form/Re-Bar 4/8/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 4/8/2022 Approved VINCENT HANLEY
Underground Mechanical 4/8/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/21/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 4/21/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Approved VINCENT HANLEY
Green Building Rough 4/21/2022 Approved VINCENT HANLEY
HVAC-Rough 4/21/2022 Approved VINCENT HANLEY
Insulation 4/21/2022 Approved VINCENT HANLEY
PLUMBING-Rough 4/21/2022 Approved VINCENT HANLEY
Drywall Nailing 4/29/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 4/29/2022 Approved MORRIS JACKSON
Final 6/30/2022 Corrections Issued JEFFREY BULL
Green Building Final 6/30/2022 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 6/30/2022 SGSOV Approved JEFFREY BULL
Smoke Detectors 6/30/2022 Approved JEFFREY BULL
Final 7/14/2022 Partial Approval JEFFREY BULL