2487-2489 S BUTLER AVE 90064

Certificate Information: 2487-2489 S BUTLER AVE 90064

Application / Permit
21014-20000-01636
Plan Check / Job No.
B21VN03909
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 356 SQFT & REMODEL TO (E) SINGLE FAMILY DWELLING
Permit Issued
Issued on 8/13/2021
Issuing Office
Current Status
CofO Issued on 5/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 PETER MOSESIAN
Corrections Issued 5/2/2021 PETER MOSESIAN
Quality Review Completed 5/7/2021 OMID HEDAYAT
Plan Check Approved 8/13/2021 PETER MOSESIAN
Issued 8/13/2021 APPLICANT
CofO in Progress 5/17/2022 OGANES TARAKHCHYAN
Permit Finaled 5/21/2022 DANIEL ORRANTE
CofO Issued 5/21/2022 DANIEL ORRANTE
Permit Finaled 5/21/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 5/25/2021 STEVEN WECHSLER
Low Impact Development Cleared 8/4/2021 SARAH YOUSSEF
Sewer availability Cleared 8/6/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 8/9/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 8/12/2021 DINAH GARIN

Contact Information

Architect Gilliam,, Jonathan; Lic. No.: C33995 15017 ARCHWOOD STREET      VAN NUYS, CA 91405
Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/16/2021 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 8/20/2021 Approved OGANES TARAKHCHYAN
Wood Frame 8/26/2021 Partial Approval OGANES TARAKHCHYAN
Wood Frame 8/31/2021 Partial Approval OGANES TARAKHCHYAN
Special/Order Compliance 10/29/2021 Corrections Issued KENNETH NAGLE
Verify Rec and Parks Fee Memo 3/4/2022 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 3/8/2022 Approved OGANES TARAKHCHYAN
Drywall Nailing 3/8/2022 Approved OGANES TARAKHCHYAN
Final 3/8/2022 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 3/8/2022 Approved OGANES TARAKHCHYAN
Green Building Final 3/8/2022 Approved OGANES TARAKHCHYAN
Green Building Rough 3/8/2022 Approved OGANES TARAKHCHYAN
MERV13>=Final 3/8/2022 Approved OGANES TARAKHCHYAN
MERV13>=Rough 3/8/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/8/2022 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 3/8/2022 Approved OGANES TARAKHCHYAN
Final 5/11/2022 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Final 5/13/2022 Approved OGANES TARAKHCHYAN
HVAC-Final 5/13/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Final 5/13/2022 Approved OGANES TARAKHCHYAN
Final 5/16/2022 OK to Issue CofO OGANES TARAKHCHYAN