6012 S 6TH AVE 90043
Certificate Information: 6012 S 6TH AVE 90043
- Application / Permit
- 21014-20000-01629
- Plan Check / Job No.
- B21VN03893
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 17'-4" X 6' ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 12/10/2021
- Issuing Office
- Current Status
- Issued on 12/10/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 5/15/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 11/18/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 11/24/2021 | APPLICANT |
| Issued | 12/10/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/29/2021 | RENZ SORIANO |
| Construction near power lines | Cleared | 9/7/2021 | RIDWAN HARDY |
| Sewer availability | Cleared | 11/2/2021 | PAMELA TENEZA |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2021 | PAMELA TENEZA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/25/2022 | Partial Inspection | FREDDIE RIVERA |
| Sewer | 2/25/2022 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 3/7/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 5/9/2022 | Approved | HORACE FULTZ |
| ELECTRICAL-Rough | 5/9/2022 | Approved | HORACE FULTZ |
| Green Building Rough | 5/9/2022 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 5/9/2022 | Approved | HORACE FULTZ |
| Insulation | 5/13/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 6/3/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 8/24/2022 | Approved | ENRIQUE MIRELES |
| Final | 8/24/2022 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 8/24/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 8/24/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 8/24/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 8/24/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 8/24/2022 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 8/24/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 9/7/2022 | Approved | ENRIQUE MIRELES |
| Final | 9/7/2022 | Conditional Approval | ENRIQUE MIRELES |
| HVAC-Final | 9/7/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 9/7/2022 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 9/7/2022 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 9/22/2022 | Approved | ENRIQUE MIRELES |