3966 W SENECA AVE 90039

Certificate Information: 3966 W SENECA AVE 90039

Application / Permit
21014-20000-01627
Plan Check / Job No.
B21VN03888
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
237 SQ. FT. ADDITION AND INTERIOR REMODEL TO INCLUDE THE (E) KITCHEN OF SFD.
Permit Issued
Issued on 9/9/2021
Issuing Office
Current Status
CofO Issued on 2/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2021 APPLICANT
Assigned to Plan Check Engineer 4/5/2021 LUISANGEL VALENZUELA
Corrections Issued 4/5/2021 LUISANGEL VALENZUELA
Applicant returned to address corrections 8/23/2021 LUISANGEL VALENZUELA
Issued 9/9/2021 APPLICANT
Building Plans Picked Up 9/14/2021 APPLICANT
CofO in Progress 12/13/2022 COREY HUPP
CofO Issued 2/13/2023 DANIEL SANCHEZ
Permit Finaled 2/13/2023 DANIEL SANCHEZ

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/14/2021 WALLIE JONG
Sewer availability Cleared 4/14/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/15/2021 WALLIE JONG
ZI Cleared 4/15/2021 LAUREN PADICK

Contact Information

Contractor Pearl Remodeling; Lic. No.: 955824-B 6803 YARMOUTH AVENUE      RESEDA, CA 91335
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

RUBEN PEREZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT NILES, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
MARK BEVELAQUA, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL SANCHEZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
COREY HUPP, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
EMIL OPFFER, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/8/2021 Partial Approval TIMOTHY MCCURDY
Footing/Foundation/Slab 12/8/2021 Corrections Issued TIMOTHY MCCURDY
Special/Order Compliance 12/8/2021 Partial Inspection PIERRE VEGA
BUILDING-Rough-Frame 12/14/2021 Partial Approval ALFREDO BALANDRA
Special/Order Compliance 12/14/2021 Partial Inspection PIERRE VEGA
Floor/Roof Diaphrgm/Shear Wall 12/29/2021 Corrections Issued TIMOTHY MCCURDY
Special/Order Compliance 12/29/2021 Partial Inspection PIERRE VEGA
Floor/Roof Diaphrgm/Shear Wall 1/7/2022 Partial Approval TIMOTHY MCCURDY
Rough-Elec/Plmb/HVAC 1/25/2022 Corrections Issued ALFREDO BALANDRA
BUILDING-Rough-Frame 2/14/2022 Corrections Issued ALFREDO BALANDRA
Green Building Rough 2/14/2022 Corrections Issued ALFREDO BALANDRA
HVAC-Rough 2/14/2022 Corrections Issued ALFREDO BALANDRA
PLUMBING-Rough 2/14/2022 Corrections Issued ALFREDO BALANDRA
Floor/Roof Diaphrgm/Shear Wall 2/28/2022 Approved TIMOTHY MCCURDY
PLUMBING-Rough 2/28/2022 Approved TIMOTHY MCCURDY
Rough-Elec/Plmb/HVAC 2/28/2022 Corrections Issued TIMOTHY MCCURDY
BUILDING-Rough-Frame 3/9/2022 Approved TIMOTHY MCCURDY
Green Building Rough 3/9/2022 Approved TIMOTHY MCCURDY
Insulation 3/9/2022 Approved TIMOTHY MCCURDY
Interior/Exterior Lathing 3/9/2022 Partial Approval TIMOTHY MCCURDY
Shower Pan 3/9/2022 Approved TIMOTHY MCCURDY
Interior/Exterior Lathing 3/22/2022 Corrections Issued TIMOTHY MCCURDY
Drywall Nailing 4/4/2022 Approved ALFREDO BALANDRA
Shower Pan 4/4/2022 Partial Inspection ALFREDO BALANDRA
Interior/Exterior Lathing 4/14/2022 Approved COREY HUPP
Service/Power Release 6/3/2022 Not Ready for Inspection ALFREDO BALANDRA
Final 7/11/2022 Corrections Issued ROBERT MINASSIANS
Footing/Foundation/Slab 7/11/2022 Approved ROBERT MINASSIANS
Green Building Final 7/11/2022 Corrections Issued ROBERT MINASSIANS
SGSOV-Seismic Gas S/O Valve 7/11/2022 SGSOV Not Ready ROBERT MINASSIANS
Service/Power Release 7/11/2022 Approved ROBERT MINASSIANS
Smoke Detectors 7/11/2022 Approved ROBERT MINASSIANS
Final 8/22/2022 Not Ready for Inspection ALFREDO BALANDRA
Green Building Final 8/22/2022 Approved ALFREDO BALANDRA
SGSOV-Seismic Gas S/O Valve 8/22/2022 SGSOV Not Ready ALFREDO BALANDRA
Final 8/29/2022 Not Ready for Inspection COREY HUPP
SGSOV-Seismic Gas S/O Valve 8/29/2022 SGSOV Not Ready COREY HUPP
Final 11/22/2022 No Access for Inspection COREY HUPP
SGSOV-Seismic Gas S/O Valve 11/22/2022 SGSOV Not Ready COREY HUPP
Final 11/28/2022 Not Ready for Inspection COREY HUPP
SGSOV-Seismic Gas S/O Valve 11/28/2022 SGSOV Not Ready COREY HUPP
Final 12/1/2022 Corrections Issued COREY HUPP
Final 12/9/2022 OK to Issue CofO COREY HUPP
SGSOV-Seismic Gas S/O Valve 12/9/2022 SGSOV Approved COREY HUPP