3966 W SENECA AVE 90039
Certificate Information: 3966 W SENECA AVE 90039
- Application / Permit
- 21014-20000-01627
- Plan Check / Job No.
- B21VN03888
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 237 SQ. FT. ADDITION AND INTERIOR REMODEL TO INCLUDE THE (E) KITCHEN OF SFD.
- Permit Issued
- Issued on 9/9/2021
- Issuing Office
- Current Status
- CofO Issued on 2/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2021 | LUISANGEL VALENZUELA |
| Corrections Issued | 4/5/2021 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 8/23/2021 | LUISANGEL VALENZUELA |
| Issued | 9/9/2021 | APPLICANT |
| Building Plans Picked Up | 9/14/2021 | APPLICANT |
| CofO in Progress | 12/13/2022 | COREY HUPP |
| CofO Issued | 2/13/2023 | DANIEL SANCHEZ |
| Permit Finaled | 2/13/2023 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/14/2021 | WALLIE JONG |
| Sewer availability | Cleared | 4/14/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2021 | WALLIE JONG |
| ZI | Cleared | 4/15/2021 | LAUREN PADICK |
Contact Information
| Contractor | Pearl Remodeling; Lic. No.: 955824-B | 6803 YARMOUTH AVENUE RESEDA, CA 91335 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| RUBEN PEREZ, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT NILES, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK BEVELAQUA, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL SANCHEZ, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| COREY HUPP, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| EMIL OPFFER, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/8/2021 | Partial Approval | TIMOTHY MCCURDY |
| Footing/Foundation/Slab | 12/8/2021 | Corrections Issued | TIMOTHY MCCURDY |
| Special/Order Compliance | 12/8/2021 | Partial Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 12/14/2021 | Partial Approval | ALFREDO BALANDRA |
| Special/Order Compliance | 12/14/2021 | Partial Inspection | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2021 | Corrections Issued | TIMOTHY MCCURDY |
| Special/Order Compliance | 12/29/2021 | Partial Inspection | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2022 | Partial Approval | TIMOTHY MCCURDY |
| Rough-Elec/Plmb/HVAC | 1/25/2022 | Corrections Issued | ALFREDO BALANDRA |
| BUILDING-Rough-Frame | 2/14/2022 | Corrections Issued | ALFREDO BALANDRA |
| Green Building Rough | 2/14/2022 | Corrections Issued | ALFREDO BALANDRA |
| HVAC-Rough | 2/14/2022 | Corrections Issued | ALFREDO BALANDRA |
| PLUMBING-Rough | 2/14/2022 | Corrections Issued | ALFREDO BALANDRA |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2022 | Approved | TIMOTHY MCCURDY |
| PLUMBING-Rough | 2/28/2022 | Approved | TIMOTHY MCCURDY |
| Rough-Elec/Plmb/HVAC | 2/28/2022 | Corrections Issued | TIMOTHY MCCURDY |
| BUILDING-Rough-Frame | 3/9/2022 | Approved | TIMOTHY MCCURDY |
| Green Building Rough | 3/9/2022 | Approved | TIMOTHY MCCURDY |
| Insulation | 3/9/2022 | Approved | TIMOTHY MCCURDY |
| Interior/Exterior Lathing | 3/9/2022 | Partial Approval | TIMOTHY MCCURDY |
| Shower Pan | 3/9/2022 | Approved | TIMOTHY MCCURDY |
| Interior/Exterior Lathing | 3/22/2022 | Corrections Issued | TIMOTHY MCCURDY |
| Drywall Nailing | 4/4/2022 | Approved | ALFREDO BALANDRA |
| Shower Pan | 4/4/2022 | Partial Inspection | ALFREDO BALANDRA |
| Interior/Exterior Lathing | 4/14/2022 | Approved | COREY HUPP |
| Service/Power Release | 6/3/2022 | Not Ready for Inspection | ALFREDO BALANDRA |
| Final | 7/11/2022 | Corrections Issued | ROBERT MINASSIANS |
| Footing/Foundation/Slab | 7/11/2022 | Approved | ROBERT MINASSIANS |
| Green Building Final | 7/11/2022 | Corrections Issued | ROBERT MINASSIANS |
| SGSOV-Seismic Gas S/O Valve | 7/11/2022 | SGSOV Not Ready | ROBERT MINASSIANS |
| Service/Power Release | 7/11/2022 | Approved | ROBERT MINASSIANS |
| Smoke Detectors | 7/11/2022 | Approved | ROBERT MINASSIANS |
| Final | 8/22/2022 | Not Ready for Inspection | ALFREDO BALANDRA |
| Green Building Final | 8/22/2022 | Approved | ALFREDO BALANDRA |
| SGSOV-Seismic Gas S/O Valve | 8/22/2022 | SGSOV Not Ready | ALFREDO BALANDRA |
| Final | 8/29/2022 | Not Ready for Inspection | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 8/29/2022 | SGSOV Not Ready | COREY HUPP |
| Final | 11/22/2022 | No Access for Inspection | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Not Ready | COREY HUPP |
| Final | 11/28/2022 | Not Ready for Inspection | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 11/28/2022 | SGSOV Not Ready | COREY HUPP |
| Final | 12/1/2022 | Corrections Issued | COREY HUPP |
| Final | 12/9/2022 | OK to Issue CofO | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 12/9/2022 | SGSOV Approved | COREY HUPP |