9943 N COLLETT AVE 91343
Certificate Information: 9943 N COLLETT AVE 91343
- Application / Permit
- 21014-20000-01624
- Plan Check / Job No.
- B21VN03883
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 20' DETACHED GARAGE AND ADD 10' X 14' FOR (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(B). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 3/22/2022
- Issuing Office
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2021 | JENNIFER LEE |
| Corrections Issued | 4/8/2021 | JENNIFER LEE |
| Plan Check Approved | 10/12/2021 | JENNIFER LEE |
| Building Plans Picked Up | 10/14/2021 | APPLICANT |
| Issued | 3/22/2022 | APPLICANT |
| CofO in Progress | 10/11/2022 | JAVIER RAMOS JR |
| CofO Issued | 12/17/2022 | MICHAEL SMITH |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/6/2021 | JENNIFER LEE |
| Address approval | Cleared | 5/21/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2021 | GABRIEL ROBLES |
| Permit | Cleared | 5/21/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 5/21/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/21/2021 | GABRIEL ROBLES |
| Trees in Parkway | Cleared | 9/23/2021 | JOEL HERNANDEZ |
| Construction near power lines | Cleared | 9/29/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 16200 VENTURA BLVD STE 317 ENCINO, CA 91436 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/4/2022 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 4/12/2022 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/4/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/6/2022 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/16/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/16/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 5/16/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/16/2022 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/16/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/23/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 5/23/2022 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 5/23/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 5/23/2022 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/23/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 6/2/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 6/2/2022 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 6/2/2022 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/3/2022 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 7/8/2022 | Approved | DEANDRE HOFFMAN |
| Final | 7/25/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Green Building Final | 7/25/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 7/25/2022 | SGSOV Approved | DEANDRE HOFFMAN |
| Smoke Detectors | 7/25/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Final | 8/2/2022 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 8/2/2022 | Approved | JAVIER RAMOS JR |
| Green Building Final | 8/2/2022 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 8/2/2022 | Approved | JAVIER RAMOS JR |
| Final | 8/9/2022 | Conditional Approval | JAVIER RAMOS JR |
| Final | 8/25/2022 | Corrections Issued | JAVIER RAMOS JR |
| Final | 10/11/2022 | OK to Issue CofO | JAVIER RAMOS JR |