4416 N LAURELGROVE AVE 91604

Certificate Information: 4416 N LAURELGROVE AVE 91604

Application / Permit
21014-20000-01598
Plan Check / Job No.
B21VN03828
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 7'6" X 31'4" IRREGULAR SHAPED ADDITION TO (E) SFD TO ENLARGE AND RELOCATE THE KITCHEN AT 1ST FLOOR, ENCLOSE (E) 4' X 17'6" FRONT PORCH TO ENLARGE THE LIVING ROOM , NEW 28' X 29'6" 2ND FLOOR ADDITION TO (E) SFD TO CREATE (2) BEDROOMS , DEN AND STAIRCASE , INTERIOR REMODEL TO (E) SFD TO REMODEL DINING ROOM , LIVING ROOM , (2) BEDROOMS , (2)BATHROOMS , NFPA-13D FIRE SPRINKLERS REQUIRED THORUGHOUT , ALL WORK PER ENGINEERING
Permit Issued
Issued on 11/30/2021
Issuing Office
Current Status
CofO Issued on 7/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2021 APPLICANT
Assigned to Plan Check Engineer 5/6/2021 RARES BODEA
Corrections Issued 5/14/2021 RARES BODEA
Quality Review Completed 5/20/2021 STEVEN KIM
Building Plans Picked Up 5/21/2021 APPLICANT
Applicant returned to address corrections 11/22/2021 RARES BODEA
Plan Check Approved 11/29/2021 RARES BODEA
Issued 11/30/2021 APPLICANT
CofO in Progress 6/29/2023 CHRISTOPHE COCHRAN
Permit Finaled 7/6/2023 MICHAEL SMITH
CofO Issued 7/6/2023 MICHAEL SMITH
Permit Finaled 7/6/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/15/2021 DAGOVERTO GUERRERO
Construction near power lines Cleared 10/4/2021 RIDWAN HARDY
Low Impact Development Cleared 10/27/2021 NICK RAYGOZA
Roof/Waste drainage to street Cleared 11/16/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 11/16/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Mnm Remodeling Inc; Lic. No.: 1003511-B 6200 CANOGA AVE SUITE 207      WOODLAND HILLS, CA 91367
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/19/2022 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 1/24/2022 Conditional Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 2/15/2022 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 2/15/2022 Approved ARAM AVEDISIAN
PLUMBING-Rough 2/15/2022 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 2/17/2022 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 3/8/2022 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 7/13/2022 Conditional Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 7/13/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 7/13/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 7/13/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 7/13/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 8/2/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/2/2022 Partial Approval CHRISTOPHE COCHRAN
Shower Pan 8/2/2022 Approved CHRISTOPHE COCHRAN
Insulation 8/8/2022 Approved CHRISTOPHE COCHRAN
Drywall Nailing 8/11/2022 No Access for Inspection JACK KARGODORIAN
Drywall Nailing 8/16/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 10/19/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 10/31/2022 SGSOV Not Ready CHRISTOPHE COCHRAN
ELECTRICAL-Final 3/8/2023 Approved CHRISTOPHE COCHRAN
Final 3/8/2023 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 3/8/2023 Approved CHRISTOPHE COCHRAN
HVAC-Final 3/8/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 3/8/2023 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 3/8/2023 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 3/8/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 3/8/2023 Approved CHRISTOPHE COCHRAN
Final 6/29/2023 OK to Issue CofO CHRISTOPHE COCHRAN