5548-5550 N OSO AVE 91367
Certificate Information: 5548-5550 N OSO AVE 91367
- Application / Permit
- 21014-20000-01592
- Plan Check / Job No.
- B21VN03815
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD NEW ADU IRRIGULAR ADDITION 924.5 SQFT TO (E) SFD (22'-10" x 55'-10") W/ NEW NFPA 13D SPRINKLERS THROUGHOUT SFD AND ADU PER LAMC 12.22 A.33(c) AND (e)
- Permit Issued
- Issued on 12/20/2021
- Issuing Office
- Current Status
- CofO Issued on 10/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/31/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | PETER MOSESIAN |
| Corrections Issued | 5/1/2021 | PETER MOSESIAN |
| Quality Review Completed | 5/10/2021 | OMID HEDAYAT |
| Plan Check Approved | 12/17/2021 | JON BLAINE |
| Issued | 12/20/2021 | APPLICANT |
| CofO in Progress | 10/14/2022 | STEVEN BACK |
| CofO Issued | 10/19/2022 | JOHN JANSON |
| Permit Finaled | 10/19/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/1/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/3/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2021 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 6/7/2021 | BRIAN MILLER |
| ZA Case | Cleared | 6/8/2021 | DANG NGUYEN |
| Hydrant and Access approval | Cleared | 8/9/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/27/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 10/29/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Green Works Construction & Design Inc; Lic. No.: 936962-B | 20301 VENTURA BLVD #222 WOODLAND HILLS, CA 91364 |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/28/2022 | Partial Approval | STEVEN BACK |
| Deputy Drilled-In Anchors | 2/3/2022 | Conditional Approval | STEVEN BACK |
| Footing/Foundation/Slab | 2/4/2022 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 2/11/2022 | No Access for Inspection | STEVEN BACK |
| Footing/Foundation/Slab | 2/17/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 3/30/2022 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2022 | Partial Approval | STEVEN BACK |
| HVAC-Rough | 3/30/2022 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 4/1/2022 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 4/1/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2022 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 4/1/2022 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 4/1/2022 | Approved | STEVEN BACK |
| MERV13>=Rough | 4/1/2022 | Approved | STEVEN BACK |
| PLUMBING-Rough | 4/1/2022 | Approved | STEVEN BACK |
| Deputy Wood Construction | 4/13/2022 | Conditional Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 4/18/2022 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 4/18/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/18/2022 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 4/18/2022 | Approved | VINCENT HANLEY |
| Shower Pan | 4/18/2022 | Approved | VINCENT HANLEY |
| Final | 4/21/2022 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Approved | STEVEN BACK |
| Insulation | 4/21/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 4/26/2022 | Partial Approval | STEVEN BACK |
| Verify Sprinkler Sign Off | 4/26/2022 | Conditional Approval | STEVEN BACK |
| Drywall Nailing | 5/3/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 5/9/2022 | Approved | STEVEN BACK |
| Sewer | 7/21/2022 | Approved | STEVEN BACK |
| Underground Mechanical | 7/21/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 9/20/2022 | Conditional Approval | STEVEN BACK |
| ELECTRICAL-Final | 9/20/2022 | Approved | STEVEN BACK |
| Final | 9/20/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Final | 9/20/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 9/20/2022 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 9/20/2022 | Approved | STEVEN BACK |
| Verify Sprinkler Sign Off | 9/20/2022 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 10/14/2022 | Approved | STEVEN BACK |
| Final | 10/14/2022 | OK to Issue CofO | STEVEN BACK |
| Green Building Final | 10/14/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 10/14/2022 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 10/14/2022 | Approved | STEVEN BACK |
| Verify Sprinkler Sign Off | 10/14/2022 | Approved | STEVEN BACK |