6447 W MARYLAND DR 90048

Certificate Information: 6447 W MARYLAND DR 90048

Application / Permit
21014-20000-01591
Plan Check / Job No.
B21VN03810
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION TO THE (E) 2-STORY SINGLE FAMILY DWELLING. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/18/2021
Issuing Office
Current Status
CofO Issued on 4/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2021 APPLICANT
Assigned to Plan Check Engineer 4/8/2021 COLIN LOREDO
Corrections Issued 4/12/2021 COLIN LOREDO
Quality Review Completed 4/13/2021 OMID HEDAYAT
Plan Check Approved 6/4/2021 COLIN LOREDO
Issued 6/18/2021 APPLICANT
CofO in Progress 4/25/2022 EVAN COOPER
Permit Finaled 4/28/2022 DANIEL ORRANTE
CofO Issued 4/28/2022 DANIEL ORRANTE
Permit Finaled 4/28/2022 DANIEL ORRANTE

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Khanlou,, Amir; Lic. No.: C87550 10671 HOLMAN AVE   APT 207    LOS ANGELES, CA 90024

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/21/2021 Corrections Issued KEVIN SARGSYAN
METHANE-Barrier 7/21/2021 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 7/21/2021 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 7/30/2021 Corrections Issued KEVIN SARGSYAN
METHANE-Barrier 7/30/2021 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 7/30/2021 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 8/3/2021 Partial Approval EVAN COOPER
METHANE-Barrier 8/3/2021 Approved EVAN COOPER
METHANE-Subgrade 8/3/2021 Approved EVAN COOPER
ELECTRICAL-Rough 9/27/2021 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 9/28/2021 Approved EVAN COOPER
ELECTRICAL-Rough 10/5/2021 Approved EVAN COOPER
PLUMBING-Rough 10/5/2021 Approved EVAN COOPER
Shower Pan 10/5/2021 Approved EVAN COOPER
Wood Frame 10/5/2021 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 10/6/2021 Not Ready for Inspection EVAN COOPER
Green Building Rough 10/6/2021 Approved EVAN COOPER
Insulation 10/6/2021 Not Ready for Inspection EVAN COOPER
METHANE-Rough 10/6/2021 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 10/18/2021 Not Ready for Inspection OGANES TARAKHCHYAN
METHANE-Rough 10/18/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Insulation 10/19/2021 Approved OGANES TARAKHCHYAN
Insulation 10/21/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 10/21/2021 Partial Approval OGANES TARAKHCHYAN
Insulation 10/25/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 11/3/2021 Approved DEANDRE HOFFMAN
Drywall Nailing 11/3/2021 Approved DEANDRE HOFFMAN
HVAC-Rough 11/3/2021 Approved DEANDRE HOFFMAN
METHANE-Rough 11/3/2021 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 11/8/2021 Partial Inspection EVAN COOPER
PLUMBING-Final 3/10/2022 Approved EVAN COOPER
ELECTRICAL-Final 3/16/2022 Approved EVAN COOPER
Final 3/23/2022 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 3/23/2022 Approved EVAN COOPER
Green Building Final 3/23/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 3/23/2022 SGSOV Approved EVAN COOPER
Smoke Detectors 3/23/2022 Approved EVAN COOPER
Final 4/25/2022 OK to Issue CofO EVAN COOPER