8020 N LOUISE AVE 91325
Certificate Information: 8020 N LOUISE AVE 91325
- Application / Permit
- 21014-20000-01568
- Plan Check / Job No.
- B21VN03759
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 36' X 29'-9" ADDITION TO AND CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d).
- Permit Issued
- Issued on 11/20/2021
- Issuing Office
- Current Status
- CofO Issued on 10/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/31/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/3/2021 | SERGIO MUNIZ |
| Corrections Issued | 4/3/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 9/30/2021 | SERGIO MUNIZ |
| Plan Check Approved | 10/25/2021 | SERGIO MUNIZ |
| Issued | 11/20/2021 | APPLICANT |
| Building Plans Picked Up | 11/30/2021 | APPLICANT |
| CofO in Progress | 8/10/2023 | RAUL OLAGI |
| Permit Finaled | 10/23/2023 | RUBEN SALAS |
| CofO Issued | 10/23/2023 | RUBEN SALAS |
| Permit Finaled | 10/23/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/19/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/19/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 9/16/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 9/17/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Sunternal Construction Inc; Lic. No.: 1036536-B | 5671 SANTA TERESA BLVD STE 105 SAN JOSE, CA 95123 |
| Engineer | Manlangit,, Vicente Balingasa; Lic. No.: C75499 | 7919 SAUSALITO AVE WEST HILLS, CA 91304 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/6/2021 | Partial Approval | ALAN MORELOS |
| Footing/Foundation/Slab | 1/6/2022 | Corrections Issued | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 1/10/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2022 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2022 | No Access for Inspection | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2022 | Corrections Issued | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2022 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/8/2022 | Not Ready for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 10/7/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 10/7/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 10/7/2022 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Rough | 10/7/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 10/7/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 10/17/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 10/17/2022 | Partial Approval | RAUL OLAGI |
| Insulation | 10/24/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 11/1/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 11/16/2022 | Approved | RAUL OLAGI |
| Underground Mechanical | 12/15/2022 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Final | 1/17/2023 | Corrections Issued | RAUL OLAGI |
| Final | 7/18/2023 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/18/2023 | Approved | JUAN VALENZUELA |
| Green Building Final | 7/18/2023 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 7/18/2023 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 7/18/2023 | Approved | JUAN VALENZUELA |
| Final | 7/25/2023 | Corrections Issued | RAUL OLAGI |
| Final | 8/10/2023 | OK to Issue CofO | RAUL OLAGI |