18350 W FRIAR ST 91335
Certificate Information: 18350 W FRIAR ST 91335
- Application / Permit
- 21014-20000-01552
- Plan Check / Job No.
- B21VN03737
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (17'-6"x19'-10") ADDITION OF 497 SQFT TO EXTEND THE (E) LIVING ROOM REMODEL THE (E) KITCHEN AND CONVERT THE (E) BATHROOM INTO A (N) LAUNDRY ROOM.
- Permit Issued
- Issued on 9/4/2021
- Issuing Office
- Current Status
- CofO Issued on 5/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | PETER MOSESIAN |
| Corrections Issued | 4/4/2021 | PETER MOSESIAN |
| Building Plans Picked Up | 4/8/2021 | APPLICANT |
| Issued | 9/4/2021 | APPLICANT |
| CofO in Progress | 5/6/2022 | SEAN HAUPT |
| CofO Issued | 5/21/2022 | MICHAEL SMITH |
| Permit Finaled | 5/21/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/30/2021 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 7/20/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/3/2021 | ABDULLAH SADOZAI |
| ZI | Cleared | 8/3/2021 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/17/2021 | Conditional Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 9/23/2021 | Approved | RONALD COWAN |
| Insulation | 10/4/2021 | Partial Approval | JAVIER RAMOS JR |
| Wood Frame | 10/4/2021 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2021 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 10/20/2021 | Corrections Issued | SEAN HAUPT |
| Green Building Rough | 10/20/2021 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 12/22/2021 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Rough | 12/22/2021 | Approved | SEAN HAUPT |
| Green Building Rough | 12/22/2021 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 12/22/2021 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Rough | 12/22/2021 | Approved | SEAN HAUPT |
| Wood Frame | 12/22/2021 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 12/28/2021 | Approved | SEAN HAUPT |
| Green Building Rough | 12/28/2021 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 12/28/2021 | Approved | SEAN HAUPT |
| Shower Pan | 12/28/2021 | Approved | SEAN HAUPT |
| Green Building Rough | 1/6/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 1/6/2022 | Approved | SEAN HAUPT |
| Insulation | 1/11/2022 | Approved | MORRIS JACKSON |
| Drywall Nailing | 1/18/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 1/18/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 4/27/2022 | Corrections Issued | SEAN HAUPT |
| Final | 4/27/2022 | Corrections Issued | SEAN HAUPT |
| Footing/Foundation/Slab | 4/27/2022 | Approved | SEAN HAUPT |
| Green Building Final | 4/27/2022 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Final | 4/27/2022 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Final | 4/27/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 4/27/2022 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 4/27/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 5/2/2022 | Not Ready for Inspection | SEAN HAUPT |
| Final | 5/2/2022 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Final | 5/2/2022 | Approved | SEAN HAUPT |
| HVAC-Final | 5/2/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 5/6/2022 | Approved | SEAN HAUPT |
| Final | 5/6/2022 | OK to Issue CofO | SEAN HAUPT |