18350 W FRIAR ST 91335

Certificate Information: 18350 W FRIAR ST 91335

Application / Permit
21014-20000-01552
Plan Check / Job No.
B21VN03737
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(17'-6"x19'-10") ADDITION OF 497 SQFT TO EXTEND THE (E) LIVING ROOM REMODEL THE (E) KITCHEN AND CONVERT THE (E) BATHROOM INTO A (N) LAUNDRY ROOM.
Permit Issued
Issued on 9/4/2021
Issuing Office
Current Status
CofO Issued on 5/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 PETER MOSESIAN
Corrections Issued 4/4/2021 PETER MOSESIAN
Building Plans Picked Up 4/8/2021 APPLICANT
Issued 9/4/2021 APPLICANT
CofO in Progress 5/6/2022 SEAN HAUPT
CofO Issued 5/21/2022 MICHAEL SMITH
Permit Finaled 5/21/2022 MICHAEL SMITH

Permit Application Clearance Information

Sewer availability Cleared 4/30/2021 ADRIAN CASTRO
Low Impact Development Cleared 7/20/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/3/2021 ABDULLAH SADOZAI
ZI Cleared 8/3/2021 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 8/19/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/17/2021 Conditional Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 9/23/2021 Approved RONALD COWAN
Insulation 10/4/2021 Partial Approval JAVIER RAMOS JR
Wood Frame 10/4/2021 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 10/7/2021 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 10/20/2021 Corrections Issued SEAN HAUPT
Green Building Rough 10/20/2021 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 12/22/2021 Corrections Issued SEAN HAUPT
ELECTRICAL-Rough 12/22/2021 Approved SEAN HAUPT
Green Building Rough 12/22/2021 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 12/22/2021 Corrections Issued SEAN HAUPT
PLUMBING-Rough 12/22/2021 Approved SEAN HAUPT
Wood Frame 12/22/2021 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 12/28/2021 Approved SEAN HAUPT
Green Building Rough 12/28/2021 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 12/28/2021 Approved SEAN HAUPT
Shower Pan 12/28/2021 Approved SEAN HAUPT
Green Building Rough 1/6/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 1/6/2022 Approved SEAN HAUPT
Insulation 1/11/2022 Approved MORRIS JACKSON
Drywall Nailing 1/18/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 1/18/2022 Approved SEAN HAUPT
ELECTRICAL-Final 4/27/2022 Corrections Issued SEAN HAUPT
Final 4/27/2022 Corrections Issued SEAN HAUPT
Footing/Foundation/Slab 4/27/2022 Approved SEAN HAUPT
Green Building Final 4/27/2022 Not Ready for Inspection SEAN HAUPT
HVAC-Final 4/27/2022 Not Ready for Inspection SEAN HAUPT
PLUMBING-Final 4/27/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 4/27/2022 SGSOV Approved SEAN HAUPT
Smoke Detectors 4/27/2022 Approved SEAN HAUPT
ELECTRICAL-Final 5/2/2022 Not Ready for Inspection SEAN HAUPT
Final 5/2/2022 Not Ready for Inspection SEAN HAUPT
Green Building Final 5/2/2022 Approved SEAN HAUPT
HVAC-Final 5/2/2022 Approved SEAN HAUPT
ELECTRICAL-Final 5/6/2022 Approved SEAN HAUPT
Final 5/6/2022 OK to Issue CofO SEAN HAUPT