4819 N MATILIJA AVE 91423
Certificate Information: 4819 N MATILIJA AVE 91423
- Application / Permit
- 21014-20000-01523
- Plan Check / Job No.
- B21VN03696
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 197 SQ. FT. ADDITION TO REAR AND 87 SQ. FT. ADDITION TO FRONT, AND INTERIOR REMODEL TO THE (E) SFD.
- Permit Issued
- Issued on 9/22/2021
- Issuing Office
- Current Status
- CofO Issued on 10/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | PETER MOSESIAN |
| Corrections Issued | 4/4/2021 | PETER MOSESIAN |
| Plan Check Approved | 9/22/2021 | PETER MOSESIAN |
| Issued | 9/22/2021 | APPLICANT |
| CofO in Progress | 10/12/2022 | DAVID MATSON |
| CofO Issued | 10/12/2022 | MICHAEL SMITH |
| Permit Finaled | 10/12/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/3/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 8/4/2021 | MATTHEW CRAIG |
| ZI | Cleared | 8/4/2021 | NOAH MCCOY |
| Roof/Waste drainage to street | Cleared | 9/9/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manoukian,, Krikor Kerop; Lic. No.: C87010 | 2310 W MAGNOLIA BLVD STE A BURBANK, CA 91506 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/28/2021 | Approved | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 11/2/2021 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 11/2/2021 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 11/4/2021 | Corrections Issued | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 11/5/2021 | Conditional Approval | MISAEL ESPARZA |
| Insulation | 11/17/2021 | Partial Approval | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2021 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 12/13/2021 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2022 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2022 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 1/31/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 1/31/2022 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/9/2022 | Conditional Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 2/9/2022 | Approved | MISAEL ESPARZA |
| Green Building Rough | 2/9/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 2/9/2022 | Corrections Issued | MISAEL ESPARZA |
| MERV13>=Rough | 2/9/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 2/9/2022 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 2/18/2022 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/18/2022 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 3/3/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 3/9/2022 | Conditional Approval | MISAEL ESPARZA |
| HVAC-Rough | 3/14/2022 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 3/30/2022 | Conditional Approval | MISAEL ESPARZA |
| Green Building Rough | 3/30/2022 | Approved | MISAEL ESPARZA |
| Grounding or Bonding | 4/19/2022 | Partial Inspection | MISAEL ESPARZA |
| Shower Pan | 5/13/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/27/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/4/2022 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 10/4/2022 | Approved | MISAEL ESPARZA |
| Final | 10/4/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 10/4/2022 | Approved | MISAEL ESPARZA |
| MERV13>=Final | 10/4/2022 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 10/4/2022 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 10/4/2022 | Approved | MISAEL ESPARZA |
| Final | 10/11/2022 | OK to Issue CofO | DAVID MATSON |