12209 W GOSHEN AVE 90049
Certificate Information: 12209 W GOSHEN AVE 90049
- Application / Permit
- 21014-20000-01522
- Plan Check / Job No.
- B21VN03695
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 19' 9" X 26' 10" IRR.-SHAPE ADDITION TO REAR OF (E) SFD. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 11/16/2021
- Issuing Office
- Current Status
- CofO Issued on 7/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 4/8/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 5/29/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 7/14/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 11/4/2021 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 11/4/2021 | APPLICANT |
| Issued | 11/16/2021 | APPLICANT |
| CofO in Progress | 7/21/2022 | OGANES TARAKHCHYAN |
| Permit Finaled | 7/29/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/29/2022 | DANIEL ORRANTE |
| CofO Issued | 7/29/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 5/14/2021 | EILEEN HUNT |
| Sewer availability | Cleared | 7/29/2021 | DINAH GARIN |
| Low Impact Development | Cleared | 8/27/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 9/14/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2021 | DINAH GARIN |
| Construction near power lines | Cleared | 10/19/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/19/2021 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2021 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2021 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/11/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 2/15/2022 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 2/15/2022 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 2/15/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 2/15/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 2/24/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 2/24/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 2/24/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 3/3/2022 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 3/3/2022 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 3/14/2022 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 6/9/2022 | Approved | KENNETH NAGLE |
| Final | 7/19/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 7/19/2022 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 7/19/2022 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 7/19/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 7/20/2022 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 7/20/2022 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 7/20/2022 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 7/20/2022 | Approved | OGANES TARAKHCHYAN |