12704 W VANOWEN ST 91605

Certificate Information: 12704 W VANOWEN ST 91605

Application / Permit
21014-20000-01521
Plan Check / Job No.
B21VN03694
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO AND CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT. PER LAMC 12.22 A.33(c) and (d) (23'-0"x20'-0")
Permit Issued
Issued on 10/4/2021
Issuing Office
Current Status
CofO Issued on 1/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 ALFREDO JARA
Corrections Issued 4/6/2021 ALFREDO JARA
Applicant returned to address corrections 7/9/2021 MOHAMMAD ESMAILI
Building Plans Picked Up 7/12/2021 APPLICANT
Plan Check Approved 10/2/2021 MOHAMMAD ESMAILI
Issued 10/4/2021 APPLICANT
CofO in Progress 1/5/2023 JOHN COLEMAN
CofO in Progress 1/19/2023 ROBERT GOLD
Permit Finaled 1/21/2023 MICHAEL SMITH
CofO Issued 1/21/2023 MICHAEL SMITH
Permit Finaled 1/21/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/9/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 4/9/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/13/2021 LEE GUILBEAUX
Sewer availability Cleared 4/13/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/13/2021 LEE GUILBEAUX
ZA Case Cleared 4/14/2021 MIGUEL GAMBOA
Hydrant and Access approval Cleared 5/24/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Kator,, Khaled; Lic. No.: C69781 19519 TULSA ST      NORTHRIDGE, CA 91326

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/21/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 1/21/2022 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 2/16/2022 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 4/4/2022 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 4/4/2022 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 4/4/2022 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 4/4/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 4/4/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 5/17/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 5/17/2022 Partial Approval CHRISTOPHE COCHRAN
Sewer 5/17/2022 Approved CHRISTOPHE COCHRAN
Insulation 5/26/2022 Approved CHRISTOPHE COCHRAN
Shower Pan 5/26/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 6/6/2022 Corrections Issued CALEB MEISTER
HVAC-Rough 6/21/2022 Corrections Issued RAFAEL CORTES
HVAC-Rough 7/1/2022 Approved RAFAEL CORTES
Drywall Nailing 8/19/2022 Approved RAFAEL CORTES
Final 8/19/2022 Corrections Issued RAFAEL CORTES
Footing/Foundation/Slab 8/19/2022 Approved RAFAEL CORTES
Green Building Final 8/19/2022 Corrections Issued RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 8/19/2022 SGSOV Approved RAFAEL CORTES
Smoke Detectors 8/19/2022 Not Ready for Inspection RAFAEL CORTES
Final 8/25/2022 Corrections Issued RAFAEL CORTES
Green Building Final 8/25/2022 Approved RAFAEL CORTES
HVAC-Final 8/25/2022 Corrections Issued RAFAEL CORTES
Smoke Detectors 8/25/2022 Corrections Issued RAFAEL CORTES
Final 10/13/2022 Not Ready for Inspection RAFAEL CORTES
HVAC-Final 10/13/2022 Approved RAFAEL CORTES
Smoke Detectors 10/13/2022 Approved RAFAEL CORTES
Final 10/25/2022 Corrections Issued THOMAS FINNILA
Final 11/21/2022 Not Ready for Inspection JOHN COLEMAN
Final 12/2/2022 Not Ready for Inspection JORDAN KUTZLY
Final 12/20/2022 OK to Issue CofO JOHN COLEMAN