1021 S CALZONA ST 90023
Certificate Information: 1021 S CALZONA ST 90023
- Application / Permit
- 21014-20000-01517
- Plan Check / Job No.
- B21VN03680
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ECPC: 340 SQ. FT. ADDITION TO THE REAR OF THE (E) SFD
- Permit Issued
- Issued on 5/10/2021
- Issuing Office
- Current Status
- CofO Issued on 12/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | RICHARD GARCIA |
| Corrections Issued | 4/4/2021 | RICHARD GARCIA |
| Plan Check Approved | 5/6/2021 | RICHARD GARCIA |
| Issued | 5/10/2021 | APPLICANT |
| CofO in Progress | 12/7/2021 | AMY COLIN |
| Permit Finaled | 12/13/2021 | DEROLD HAUFF |
| CofO Issued | 12/13/2021 | DEROLD HAUFF |
| Permit Finaled | 12/13/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/14/2021 | JEANIE LAM |
| Sewer availability | Cleared | 4/14/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2021 | JEANIE LAM |
Contact Information
| Contractor | Supreme Remodeling Inc; Lic. No.: 939981-B | 14545 VICTORY BLVD UNIT 401 VAN NUYS, CA 91411 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/7/2021 | Approved | ROBERT VORHIS |
| Footing/Foundation/Slab | 6/15/2021 | Approved | ROBERT VORHIS |
| PLUMBING-Rough | 6/15/2021 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2021 | Partial Approval | COREY HUPP |
| PLUMBING-Rough | 8/4/2021 | Not Ready for Inspection | COREY HUPP |
| Rough-Elec/Plmb/HVAC | 8/4/2021 | Not Ready for Inspection | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2021 | Partial Approval | RUBEN SALAS |
| ELECTRICAL-Rough | 8/11/2021 | Approved | COREY HUPP |
| PLUMBING-Rough | 8/11/2021 | Approved | COREY HUPP |
| Insulation | 8/16/2021 | Not Ready for Inspection | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 8/16/2021 | Approved | ASHLEY THOMPSON |
| Pre-Inspection | 8/16/2021 | Partial Inspection | ALAN MORELOS |
| Insulation | 8/18/2021 | Not Ready for Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 8/20/2021 | Approved | ROBERT VORHIS |
| Green Building Rough | 8/20/2021 | Approved | ROBERT VORHIS |
| HVAC-Rough | 8/20/2021 | Approved | ROBERT VORHIS |
| Insulation | 8/20/2021 | Approved | ROBERT VORHIS |
| MERV13>=Rough | 8/20/2021 | Approved | ROBERT VORHIS |
| Drywall Nailing | 8/26/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 10/6/2021 | Partial Approval | ROBERT VORHIS |
| Final | 11/10/2021 | Corrections Issued | ROBERT VORHIS |
| Green Building Final | 11/10/2021 | Approved | ROBERT VORHIS |
| MERV13>=Final | 11/10/2021 | Approved | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 11/10/2021 | SGSOV Approved | ROBERT VORHIS |
| Smoke Detectors | 11/10/2021 | Approved | ROBERT VORHIS |
| Final | 11/22/2021 | Corrections Issued | ROBERT VORHIS |
| ELECTRICAL-Final | 12/6/2021 | Approved | AMY COLIN |
| Final | 12/6/2021 | OK to Issue CofO | AMY COLIN |
| HVAC-Final | 12/6/2021 | Approved | AMY COLIN |
| PLUMBING-Final | 12/6/2021 | Approved | AMY COLIN |