6251 N ATOLL AVE 91401
Certificate Information: 6251 N ATOLL AVE 91401
- Application / Permit
- 21014-20000-01513
- Plan Check / Job No.
- B21VN03673
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 26' X 43'-2" IRREG SHAPED ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A. 33(c) and (d)
- Permit Issued
- Issued on 11/2/2021
- Issuing Office
- Current Status
- CofO Issued on 5/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 4/3/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/8/2021 | APPLICANT |
| Plan Check Approved | 11/2/2021 | JEROME MAGAT PALMA |
| Issued | 11/2/2021 | APPLICANT |
| CofO in Progress | 5/3/2023 | KIRK SANDERS |
| Permit Finaled | 5/9/2023 | MICHAEL SMITH |
| CofO Issued | 5/9/2023 | MICHAEL SMITH |
| Permit Finaled | 5/9/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 10/19/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 10/20/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/29/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/5/2021 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 11/5/2021 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 11/5/2021 | Corrections Issued | ASHLEY THOMPSON |
| Special/Order Compliance | 11/5/2021 | Partial Inspection | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/9/2021 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 11/9/2021 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 11/10/2021 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Wood Frame | 11/23/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/29/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 11/29/2021 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 12/2/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 12/2/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Rough-Elec/Plmb/HVAC | 12/2/2021 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 12/7/2021 | Conditional Approval | ASHLEY THOMPSON |
| Insulation | 12/7/2021 | Not Ready for Inspection | ASHLEY THOMPSON |
| Shower Pan | 12/7/2021 | Partial Approval | ASHLEY THOMPSON |
| Insulation | 12/8/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 12/8/2021 | Approved | CHRISTOPHE COCHRAN |
| Final | 4/25/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 4/25/2023 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/25/2023 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 4/25/2023 | Approved | KIRK SANDERS |
| Final | 5/2/2023 | OK to Issue CofO | KIRK SANDERS |