8120 S CHASE AVE 90045

Certificate Information: 8120 S CHASE AVE 90045

Application / Permit
21014-20000-01510
Plan Check / Job No.
B21VN03672
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ECPC: 332 SQ. FT. ADDITION AND INTERIOR REMODEL. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/11/2021
Issuing Office
Current Status
CofO Issued on 2/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/29/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 COLIN LOREDO
Corrections Issued 4/3/2021 COLIN LOREDO
Plan Check Approved 4/26/2021 COLIN LOREDO
Issued 5/11/2021 APPLICANT
CofO in Progress 2/18/2022 BOBBY KEY
Permit Finaled 2/24/2022 DANIEL ORRANTE
CofO Issued 2/24/2022 DANIEL ORRANTE
Permit Finaled 2/24/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 4/15/2021 RUBEN VASQUEZ

Contact Information

Contractor Nairn Construction Inc; Lic. No.: 1000858-B 7608 KITTYHAWK AVE      WESTCHESTER, CA 90045
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/10/2021 Approved BRENDAN LOONEY
Footing/Foundation/Slab 6/10/2021 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 6/23/2021 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 7/6/2021 Partial Inspection BRENDAN LOONEY
Green Building Rough 7/6/2021 Not Ready for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 8/26/2021 Not Ready for Inspection BRENDAN LOONEY
Green Building Rough 8/26/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 8/26/2021 Partial Approval BRENDAN LOONEY
Underground Mechanical 8/26/2021 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 9/2/2021 Partial Approval BRENDAN LOONEY
Green Building Rough 9/2/2021 Not Ready for Inspection BRENDAN LOONEY
Deputy Wood Construction 9/3/2021 Conditional Approval SHAVONNE ESPINOZA
ELECTRICAL-Rough 9/22/2021 Corrections Issued BRENDAN LOONEY
HVAC-Rough 9/22/2021 Corrections Issued BRENDAN LOONEY
Interior/Exterior Lathing 9/22/2021 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Rough 9/24/2021 Approved BRENDAN LOONEY
HVAC-Rough 9/24/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 9/24/2021 Partial Approval BRENDAN LOONEY
Insulation 10/1/2021 Approved MORRIS JACKSON
Drywall Nailing 10/12/2021 Approved JOHNNY MIRANDA
Green Building Rough 10/12/2021 Approved JOHNNY MIRANDA
Shower Pan 10/12/2021 Corrections Issued JOHNNY MIRANDA
Shower Pan 10/18/2021 Approved DAVID FEILER
Interior/Exterior Lathing 11/1/2021 Approved BOBBY KEY
BUILDING-Rough-Frame 1/21/2022 Approved BOBBY KEY
Final 1/21/2022 Corrections Issued BOBBY KEY
Gas Test 1/21/2022 Approved BOBBY KEY
PLUMBING-Final 1/21/2022 Approved BOBBY KEY
PLUMBING-Rough 1/21/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 1/21/2022 SGSOV Approved BOBBY KEY
ELECTRICAL-Final 2/1/2022 Corrections Issued BOBBY KEY
Final 2/1/2022 Corrections Issued BOBBY KEY
Green Building Final 2/1/2022 Not Ready for Inspection BOBBY KEY
HVAC-Final 2/1/2022 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 2/7/2022 Corrections Issued BOBBY KEY
HVAC-Final 2/7/2022 Approved BOBBY KEY
Smoke Detectors 2/7/2022 Approved BOBBY KEY
ELECTRICAL-Final 2/9/2022 Approved BOBBY KEY
Final 2/18/2022 OK to Issue CofO BOBBY KEY
Green Building Final 2/18/2022 Approved BOBBY KEY
PLUMBING-Final 2/18/2022 Approved BOBBY KEY