- ECPC: 155 SQ. FT. ADDITION TO AND CONVERT THE (E) 397 SQ. FT. GARAGE INTO A (N) 553 SQ. FT. ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/18/2021
- Issuing Office
- Current Status
- CofO Issued on 3/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | COLIN LOREDO |
| Corrections Issued | 4/3/2021 | COLIN LOREDO |
| Plan Check Approved | 4/29/2021 | COLIN LOREDO |
| Issued | 5/18/2021 | APPLICANT |
| CofO in Progress | 3/15/2022 | STEVEN BACK |
| Permit Finaled | 3/17/2022 | JOHN JANSON |
| CofO Issued | 3/17/2022 | JOHN JANSON |
| Permit Finaled | 3/17/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/8/2021 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 4/8/2021 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/8/2021 | JOHN TRIANTAFYLLOS |
| ZI | Cleared | 4/13/2021 | PABLO ESTRADA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/1/2021 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 9/3/2021 | Corrections Issued | HENRY KIM |
| Sewer | 9/3/2021 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 9/9/2021 | Approved | PETER FOLLING |
| PLUMBING-Rough | 9/9/2021 | Partial Approval | PETER FOLLING |
| Sewer | 9/9/2021 | Approved | PETER FOLLING |
| Deputy Drilled-In Anchors | 9/20/2021 | Conditional Approval | HENRY KIM |
| BUILDING-Rough-Frame | 10/6/2021 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 10/6/2021 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2021 | Partial Approval | HENRY KIM |
| PLUMBING-Rough | 10/6/2021 | Corrections Issued | HENRY KIM |
| Underground Mechanical | 10/6/2021 | Partial Approval | HENRY KIM |
| ELECTRICAL-Rough | 10/14/2021 | Approved | STEVEN BACK |
| HVAC-Rough | 10/14/2021 | Approved | STEVEN BACK |
| PLUMBING-Rough | 10/14/2021 | Approved | STEVEN BACK |
| Underground Mechanical | 10/14/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 11/16/2021 | Partial Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 12/3/2021 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 12/3/2021 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 12/3/2021 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 12/9/2021 | Approved | MORRIS JACKSON |
| Drywall Nailing | 12/14/2021 | Approved | JUSTIN HAWLEY |
| Shower Pan | 12/23/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 12/27/2021 | Approved | JAVIER RAMOS JR |
| Final | 3/4/2022 | Corrections Issued | STEVEN BACK |
| Green Building Final | 3/4/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 3/4/2022 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 3/4/2022 | Not Ready for Inspection | STEVEN BACK |
| Final | 3/15/2022 | OK to Issue CofO | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 3/15/2022 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 3/15/2022 | Approved | STEVEN BACK |