14250 W HORTENSE ST 91423
Certificate Information: 14250 W HORTENSE ST 91423
- Application / Permit
- 21014-20000-01499
- Plan Check / Job No.
- B21VN03658
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET. GARAGE/REC ROOM TO NEW ACCESSORY DWELLING UNIT WITH 20' x 31' SECOND STORY ADDITION PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 3/14/2022
- Issuing Office
- Current Status
- CofO Issued on 12/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | SEAN SHAHMIRI |
| Corrections Issued | 5/2/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 5/14/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 5/17/2021 | APPLICANT |
| Plan Check Approved | 3/8/2022 | SEAN SHAHMIRI |
| Issued | 3/14/2022 | APPLICANT |
| CofO in Progress | 12/5/2023 | MISAEL ESPARZA |
| Permit Finaled | 12/27/2023 | RUBEN SALAS |
| CofO Issued | 12/27/2023 | RUBEN SALAS |
| Permit Finaled | 12/27/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/19/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/19/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 1/12/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 1/24/2022 | CARLOS AGUILERA |
| ZI | Cleared | 2/24/2022 | MIGUEL GAMBOA |
Contact Information
| Contractor | Dwell Llc; Lic. No.: 1030158-B | 5315 LAUREL CANYON BLVD #102 VALLEY VILLAGE, CA 91607 |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 6250 CANOGA AVE #525 WOODLAND HILLS, CA 91367 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/28/2022 | Corrections Issued | MISAEL ESPARZA |
| Reinforced Concrete Frame | 4/29/2022 | No Access for Inspection | MISAEL ESPARZA |
| Pre-Inspection | 7/25/2022 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 8/18/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 8/18/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 8/22/2022 | Conditional Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 8/24/2022 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 10/20/2022 | Conditional Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2022 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 11/8/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 11/8/2022 | Partial Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/18/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/18/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 11/18/2022 | Approved | MISAEL ESPARZA |
| MERV13>=Rough | 11/18/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 11/18/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/30/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/30/2022 | Conditional Approval | MISAEL ESPARZA |
| Shower Pan | 11/30/2022 | Approved | MISAEL ESPARZA |
| Insulation | 12/9/2022 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 12/15/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/15/2022 | Partial Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/21/2022 | Approved | MISAEL ESPARZA |
| Sewer | 3/15/2023 | No Access for Inspection | MISAEL ESPARZA |
| Gas Test | 3/23/2023 | Corrections Issued | MISAEL ESPARZA |
| Sewer | 3/23/2023 | Approved | MISAEL ESPARZA |
| Gas Test | 4/5/2023 | Partial Approval | MISAEL ESPARZA |
| Sewer | 4/5/2023 | Approved | MISAEL ESPARZA |
| Final | 9/1/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 9/1/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Final | 9/1/2023 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 9/1/2023 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 9/1/2023 | Corrections Issued | MISAEL ESPARZA |
| Final | 10/11/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 10/11/2023 | Approved | MISAEL ESPARZA |
| MERV13>=Final | 10/11/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 10/11/2023 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 10/11/2023 | Approved | MISAEL ESPARZA |
| Final | 10/23/2023 | Conditional Approval | MISAEL ESPARZA |
| Final | 12/4/2023 | OK to Issue CofO | MISAEL ESPARZA |