5832 N PENFIELD AVE 91367

Certificate Information: 5832 N PENFIELD AVE 91367

Application / Permit
21014-20000-01491
Plan Check / Job No.
B21VN03643
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL & ADDITION TO (E) IRREGULAR SHAPED 1-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. NFPA 13D FIRE SPRINKLERS REQUIRED THROUHGOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/2/2021
Issuing Office
Current Status
CofO Issued on 10/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/25/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 COLIN LOREDO
Corrections Issued 4/6/2021 COLIN LOREDO
Quality Review Completed 4/8/2021 OMID HEDAYAT
Applicant returned to address corrections 9/9/2021 COLIN LOREDO
Applicant returned to address corrections 11/2/2021 COLIN LOREDO
Applicant returned to address corrections 11/22/2021 COLIN LOREDO
Plan Check Approved 11/22/2021 COLIN LOREDO
Issued 12/2/2021 APPLICANT
CofO in Progress 9/21/2022 SEAN HAUPT
Permit Finaled 10/13/2022 JOHN JANSON
CofO Issued 10/13/2022 JOHN JANSON
Permit Finaled 10/13/2022 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/25/2021 GABRIEL ROBLES
Sewer availability Cleared 5/25/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 7/23/2021 MATTHEW CRAIG
GPI Written Notices Cleared 9/9/2021 COLIN LOREDO
Grading Pre-Inspection Cleared 9/9/2021 COLIN LOREDO
Trees in Parkway Cleared 10/21/2021 ADALBERTO VERA
Low Impact Development Cleared 11/18/2021 TA ANH
Roof/Waste drainage to street Cleared 11/23/2021 DAGOVERTO GUERRERO
Permit Cleared 11/24/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/28/2021 No Access for Inspection SEAN HAUPT
PLUMBING-Rough 1/4/2022 Partial Approval SEAN HAUPT
Excavation/Setback/Form/Re-Bar 1/13/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 1/13/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 1/26/2022 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 2/15/2022 Corrections Issued SEAN HAUPT
HVAC-Rough 2/15/2022 Approved SEAN HAUPT
PLUMBING-Rough 2/15/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 2/22/2022 Approved SEAN HAUPT
ELECTRICAL-Rough 2/22/2022 Approved SEAN HAUPT
Shower Pan 3/1/2022 Approved JESUS PINEDA
BUILDING-Rough-Frame 3/8/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 3/8/2022 Approved SEAN HAUPT
Green Building Rough 3/8/2022 Not Ready for Inspection SEAN HAUPT
Wood Frame 3/8/2022 Approved SEAN HAUPT
Insulation 3/14/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 3/14/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 3/15/2022 Not Ready for Inspection SEAN HAUPT
Drywall Nailing 3/25/2022 Approved SEAN HAUPT
Green Building Rough 3/25/2022 Approved SEAN HAUPT
Gas Test 6/30/2022 Approved SEAN HAUPT
ELECTRICAL-Final 7/25/2022 Approved SEAN HAUPT
Final 7/25/2022 Corrections Issued SEAN HAUPT
Green Building Final 7/25/2022 Not Ready for Inspection SEAN HAUPT
HVAC-Final 7/25/2022 Approved SEAN HAUPT
PLUMBING-Final 7/25/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 7/25/2022 SGSOV Approved SEAN HAUPT
Smoke Detectors 7/25/2022 Not Ready for Inspection SEAN HAUPT
Final 9/21/2022 OK to Issue CofO SEAN HAUPT
Green Building Final 9/21/2022 Approved SEAN HAUPT
Smoke Detectors 9/21/2022 Approved SEAN HAUPT