250 N QUADRO VECCHIO DR 90272

Certificate Information: 250 N QUADRO VECCHIO DR 90272

Application / Permit
21014-20000-01488
Plan Check / Job No.
B21VN03634
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 15' X 20'-9.5" IRREGULAR SHAPED ADDITION TO ENLARGE LIVING ROOM OF (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/1/2021
Issuing Office
Current Status
Issued on 9/1/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/22/2021 APPLICANT
Assigned to Plan Check Engineer 4/28/2021 RAPHAEL ROSAS
Corrections Issued 4/29/2021 RAPHAEL ROSAS
Building Plans Picked Up 8/4/2021 APPLICANT
Issued 9/1/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/11/2021 TRACY TATE
Roof/Waste drainage to street Cleared 5/11/2021 TRACY TATE
Coastal Zone Cleared 7/28/2021 PABLO ESTRADA
ZI Cleared 7/28/2021 PABLO ESTRADA
Grading Pre-Inspection Cleared 8/2/2021 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/19/2021 Partial Inspection ANDREW NAVE
Footing/Foundation/Slab 11/3/2021 Not Ready for Inspection ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 11/12/2021 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/19/2021 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 11/19/2021 Approved ANDREW NAVE
BUILDING-Rough-Frame 12/8/2021 Partial Approval ANDREW NAVE
ELECTRICAL-Rough 12/8/2021 Approved ANDREW NAVE
Green Building Rough 12/8/2021 Not Ready for Inspection ANDREW NAVE
BUILDING-Rough-Frame 12/14/2021 Partial Approval ANDREW NAVE
Insulation 12/14/2021 Corrections Issued ANDREW NAVE
Interior/Exterior Lathing 12/14/2021 Approved ANDREW NAVE
Drywall Nailing 12/20/2021 Approved ANDREW NAVE
Insulation 12/20/2021 Approved ANDREW NAVE
BUILDING-Rough-Frame 3/11/2022 Approved ANDREW NAVE
Final 3/11/2022 Corrections Issued ANDREW NAVE
Green Building Final 3/11/2022 Corrections Issued ANDREW NAVE
Green Building Rough 3/11/2022 Approved ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 3/11/2022 SGSOV Approved ANDREW NAVE
Smoke Detectors 3/11/2022 Corrections Issued ANDREW NAVE
Final 4/13/2022 Corrections Issued ANDREW NAVE
Green Building Final 4/13/2022 Not Ready for Inspection ANDREW NAVE
Smoke Detectors 4/13/2022 Approved ANDREW NAVE