8317 N STEPHEN LANE 91304

Certificate Information: 8317 N STEPHEN LANE 91304

Application / Permit
21014-20000-01478
Plan Check / Job No.
B21VN03601
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO GAME ROOM AND ADD NEW CARPORT PER ENGINEER
Permit Issued
Issued on 4/22/2021
Issuing Office
Current Status
CofO Issued on 4/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/25/2021 APPLICANT
Assigned to Plan Check Engineer 3/30/2021 JEROME MAGAT PALMA
Corrections Issued 4/3/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 4/15/2021 JESSE ARELLANO
Issued 4/22/2021 APPLICANT
Building Plans Picked Up 4/23/2021 APPLICANT
CofO in Progress 3/1/2022 TROY SANDERS
Permit Finaled 4/26/2022 JOHN JANSON
CofO Issued 4/26/2022 JOHN JANSON
Permit Finaled 4/26/2022 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/7/2021 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 4/8/2021 GUILLERMO PETRA
ZA Case Cleared 4/8/2021 MIGUEL GAMBOA
Grading Pre-Inspection Cleared 4/21/2021 JEROME MAGAT PALMA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/18/2021 Partial Approval DAVID STEPANYAN
Footing/Foundation/Slab 8/31/2021 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 8/31/2021 Partial Approval CHRISTOPHER DELLEFIELD
Sewer 8/31/2021 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 9/14/2021 Partial Inspection DAVID STEPANYAN
ELECTRICAL-Rough 9/14/2021 Approved DAVID STEPANYAN
Green Building Rough 9/14/2021 Approved DAVID STEPANYAN
Interior/Exterior Lathing 9/14/2021 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 9/14/2021 Approved DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 9/22/2021 Not Ready for Inspection DEANDRE HOFFMAN
Insulation 9/22/2021 Approved DEANDRE HOFFMAN
BUILDING-Rough-Frame 9/27/2021 Approved DAVID STEPANYAN
Drywall Nailing 9/27/2021 Partial Approval DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 9/27/2021 Approved DAVID STEPANYAN
Interior/Exterior Lathing 9/27/2021 Not Ready for Inspection DAVID STEPANYAN
Shower Pan 9/27/2021 Approved DAVID STEPANYAN
Interior/Exterior Lathing 9/28/2021 Approved DAVID STEPANYAN
Special/Order Compliance 11/8/2021 Approved DAVID STEPANYAN
Final 2/11/2022 Partial Approval JEFFREY PARD
Green Building Final 2/11/2022 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 2/11/2022 SGSOV Approved JEFFREY PARD
Smoke Detectors 2/11/2022 Approved JEFFREY PARD
Final 2/28/2022 OK to Issue CofO TROY SANDERS
Special/Order Compliance 3/23/2022 Corrections Issued CHRIS CHRISTENSEN
Pre-Inspection 4/11/2022 Approved CHRIS CHRISTENSEN