7839 S CROYDON AVE 90045
Certificate Information: 7839 S CROYDON AVE 90045
- Application / Permit
- 21014-20000-01473
- Plan Check / Job No.
- B21VN03599
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 16' X 23' IRREGULAR SHAPED ADDITION TO (E) SINGLE FAMILY DWELLING TO ENLARGE BEDROOMS, ADD NEW BATHROOM, AND REMODEL EXISTING BATHROOM. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 3/31/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2021 | RARES BODEA |
| Corrections Issued | 3/29/2021 | RARES BODEA |
| Applicant returned to address corrections | 12/1/2021 | RARES BODEA |
| Plan Check Approved | 1/5/2022 | RARES BODEA |
| Plan Check Approved | 1/13/2023 | DANIEL ABRAMYAN |
| Issued | 3/31/2023 | APPLICANT |
| CofO in Progress | 12/20/2023 | BOBBY KEY |
| Permit Finaled | 1/10/2024 | DANIEL ORRANTE |
| CofO Issued | 1/10/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/10/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/15/2021 | VALERIA CEJA |
| Low Impact Development | Cleared | 11/10/2021 | MARCO SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2021 | TRACY TATE |
| Roof/Waste drainage to street | Cleared | 11/18/2021 | TRACY TATE |
| GPI Written Notices | Cleared | 12/2/2021 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 12/2/2021 | RARES BODEA |
Contact Information
| Contractor | New Generation Home Improvements Inc; Lic. No.: 938552-B | 5805 WHITE OAK AVE #18431 ENCINO, CA 91416 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/8/2023 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 5/10/2023 | Approved | BOBBY KEY |
| Wood Frame | 5/30/2023 | Partial Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 6/20/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 8/7/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 8/7/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 8/7/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 8/22/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 8/22/2023 | Approved | BOBBY KEY |
| Green Building Rough | 8/22/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 8/22/2023 | Approved | BOBBY KEY |
| Shower Pan | 8/22/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 8/31/2023 | Approved | BOBBY KEY |
| Insulation | 9/6/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 9/12/2023 | Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 9/12/2023 | Corrections Issued | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 12/4/2023 | SGSOV Not Ready | BOBBY KEY |
| ELECTRICAL-Final | 12/8/2023 | Corrections Issued | BOBBY KEY |
| Final | 12/8/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 12/8/2023 | Approved | BOBBY KEY |
| HVAC-Final | 12/8/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 12/8/2023 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 12/8/2023 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 12/8/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 12/19/2023 | Approved | BOBBY KEY |
| Final | 12/19/2023 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 12/19/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 12/19/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Approved | BOBBY KEY |