820 E COMMONWEALTH AVE 90291

Certificate Information: 820 E COMMONWEALTH AVE 90291

Application / Permit
21014-20000-01431
Plan Check / Job No.
B21VN03530
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 29'-3" x 12'-3" IRREGULAR SHAPE TO AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g);
Permit Issued
Issued on 7/24/2024
Issuing Office
Metro
Current Status
CofO Issued on 8/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 SELLA BENYAMIN
Corrections Issued 5/4/2021 SELLA BENYAMIN
Quality Review Completed 5/11/2021 STEVEN KIM
Applicant returned to address corrections 3/24/2022 SELLA BENYAMIN
Applicant returned to address corrections 9/1/2022 SELLA BENYAMIN
Plan Check Approved 9/29/2022 SELLA BENYAMIN
Issued 7/24/2024 APPLICANT
CofO in Progress 8/1/2025 JESUS RODRIGUEZ
Permit Finaled 8/5/2025 RICHARD STEINBACH
CofO Issued 8/5/2025 RICHARD STEINBACH
Permit Finaled 8/5/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/11/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 8/13/2021 DINAH GARIN
Sewer availability Cleared 8/13/2021 DINAH GARIN
Low Impact Development Cleared 2/3/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 3/3/2022 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 4/30/2022 JOHN CONNEALLY

Contact Information

Contractor Molina Construction Inc; Lic. No.: 938765-B 2432 SOUTHERN AVE APT A      SOUTH GATE, CA 90280
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/19/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Rough 8/20/2024 Partial Approval JESUS PINEDA
Excavation/Setback/Form/Re-Bar 9/4/2024 Conditional Approval HERBERT GIRON
Footing/Foundation/Slab 9/4/2024 Conditional Approval HERBERT GIRON
Sewer 9/18/2024 Approved HERBERT GIRON
Underground Mechanical 9/18/2024 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/2/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 10/2/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 10/17/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 10/17/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/17/2024 Partial Approval HERBERT GIRON
HVAC-Rough 10/17/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 10/17/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 10/21/2024 Approved HERBERT GIRON
HVAC-Rough 10/21/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 10/21/2024 Partial Approval HERBERT GIRON
PLUMBING-Rough 10/21/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 10/29/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Approved HERBERT GIRON
Green Building Rough 10/29/2024 Approved HERBERT GIRON
Insulation 11/13/2024 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 12/5/2024 Approved HERBERT GIRON
Insulation 12/5/2024 Corrections Issued HERBERT GIRON
Insulation 12/11/2024 Approved HERBERT GIRON
Drywall Nailing 12/30/2024 Approved MICHAEL ALLEN
Shower Pan 12/30/2024 Approved MICHAEL ALLEN
ELECTRICAL-Final 4/17/2025 Partial Approval JESUS RODRIGUEZ
Final 4/17/2025 Corrections Issued JESUS RODRIGUEZ
Green Building Final 4/17/2025 Approved JESUS RODRIGUEZ
HVAC-Final 4/17/2025 Approved JESUS RODRIGUEZ
PLUMBING-Final 4/17/2025 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 4/17/2025 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 4/17/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 8/1/2025 Approved JESUS RODRIGUEZ
Final 8/1/2025 OK to Issue CofO JESUS RODRIGUEZ