820 E COMMONWEALTH AVE 90291
Certificate Information: 820 E COMMONWEALTH AVE 90291
- Application / Permit
- 21014-20000-01431
- Plan Check / Job No.
- B21VN03530
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 29'-3" x 12'-3" IRREGULAR SHAPE TO AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g);
- Permit Issued
- Issued on 7/24/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | SELLA BENYAMIN |
| Corrections Issued | 5/4/2021 | SELLA BENYAMIN |
| Quality Review Completed | 5/11/2021 | STEVEN KIM |
| Applicant returned to address corrections | 3/24/2022 | SELLA BENYAMIN |
| Applicant returned to address corrections | 9/1/2022 | SELLA BENYAMIN |
| Plan Check Approved | 9/29/2022 | SELLA BENYAMIN |
| Issued | 7/24/2024 | APPLICANT |
| CofO in Progress | 8/1/2025 | JESUS RODRIGUEZ |
| Permit Finaled | 8/5/2025 | RICHARD STEINBACH |
| CofO Issued | 8/5/2025 | RICHARD STEINBACH |
| Permit Finaled | 8/5/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 8/11/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2021 | DINAH GARIN |
| Sewer availability | Cleared | 8/13/2021 | DINAH GARIN |
| Low Impact Development | Cleared | 2/3/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 3/3/2022 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 4/30/2022 | JOHN CONNEALLY |
Contact Information
| Contractor | Molina Construction Inc; Lic. No.: 938765-B | 2432 SOUTHERN AVE APT A SOUTH GATE, CA 90280 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/19/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 8/20/2024 | Partial Approval | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 9/4/2024 | Conditional Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 9/4/2024 | Conditional Approval | HERBERT GIRON |
| Sewer | 9/18/2024 | Approved | HERBERT GIRON |
| Underground Mechanical | 9/18/2024 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2024 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 10/2/2024 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/17/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 10/17/2024 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Partial Approval | HERBERT GIRON |
| HVAC-Rough | 10/17/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 10/17/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 10/21/2024 | Approved | HERBERT GIRON |
| HVAC-Rough | 10/21/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 10/21/2024 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 10/21/2024 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/29/2024 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | Approved | HERBERT GIRON |
| Green Building Rough | 10/29/2024 | Approved | HERBERT GIRON |
| Insulation | 11/13/2024 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 12/5/2024 | Approved | HERBERT GIRON |
| Insulation | 12/5/2024 | Corrections Issued | HERBERT GIRON |
| Insulation | 12/11/2024 | Approved | HERBERT GIRON |
| Drywall Nailing | 12/30/2024 | Approved | MICHAEL ALLEN |
| Shower Pan | 12/30/2024 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 4/17/2025 | Partial Approval | JESUS RODRIGUEZ |
| Final | 4/17/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 4/17/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 4/17/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 4/17/2025 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/17/2025 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 4/17/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 8/1/2025 | Approved | JESUS RODRIGUEZ |
| Final | 8/1/2025 | OK to Issue CofO | JESUS RODRIGUEZ |