7220 N RUBIO AVE 91406

Certificate Information: 7220 N RUBIO AVE 91406

Application / Permit
21014-20000-01362
Plan Check / Job No.
B21VN03397
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ECPC: 440 SQ. FT. ADDITION TO THE (E) SINGLE FAMILY DWELLING AND INTERIOR REMODEL. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/2/2021
Issuing Office
Current Status
CofO Issued on 2/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 COLIN LOREDO
Corrections Issued 4/17/2021 COLIN LOREDO
Plan Check Approved 5/19/2021 COLIN LOREDO
Issued 6/2/2021 APPLICANT
CofO in Progress 2/8/2022 RAUL OLAGI
No Progress 2/9/2022 MICHAEL SMITH
CofO in Progress 2/10/2022 MICHAEL SMITH
CofO Issued 2/10/2022 MICHAEL SMITH
Permit Finaled 2/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/14/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/14/2021 CARLOS AGUILERA
Sewer availability Cleared 5/14/2021 CARLOS AGUILERA

Contact Information

Architect Tohill,, Kevin Patrick; Lic. No.: C32787 3790 LIGHTNING RIDGE WAY      SIMI VALLEY, CA 93063
Contractor Gabe Kaprelian Electrical Contractor; Lic. No.: 321040-B 7220 RUBIO AVE      VAN NUYS, CA 91406
Engineer Basma,, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/9/2021 Approved DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 8/12/2021 Approved JACK KARGODORIAN
Insulation 8/23/2021 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 8/23/2021 Partial Approval DAVID STEPANYAN
Wood Frame 8/23/2021 Corrections Issued DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 8/26/2021 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 9/22/2021 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 9/22/2021 Approved JACK KARGODORIAN
Green Building Rough 9/22/2021 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 9/22/2021 Approved JACK KARGODORIAN
PLUMBING-Rough 9/22/2021 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 10/7/2021 Approved JACK KARGODORIAN
Green Building Rough 10/7/2021 Approved JACK KARGODORIAN
Insulation 10/7/2021 Approved JACK KARGODORIAN
Interior/Exterior Lathing 10/7/2021 Partial Approval JACK KARGODORIAN
Drywall Nailing 11/15/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 11/15/2021 Partial Approval ALAN MORELOS
Final 2/8/2022 OK to Issue CofO RAUL OLAGI
Footing/Foundation/Slab 2/8/2022 Approved RAUL OLAGI
Green Building Final 2/8/2022 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 2/8/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 2/8/2022 Approved RAUL OLAGI
Special/Order Compliance 2/8/2022 Partial Inspection ALAN MORELOS