13753 W SYLVAN ST 91401

Certificate Information: 13753 W SYLVAN ST 91401

Application / Permit
21014-20000-01360
Plan Check / Job No.
B21VN03392
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
41' X 22'-6" ADDITION TO (E) DETACHED GARAGE AND CONVERT GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d).
Permit Issued
Issued on 11/16/2021
Issuing Office
Current Status
CofO Issued on 3/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2021 APPLICANT
Assigned to Plan Check Engineer 5/10/2021 SERGIO MUNIZ
Corrections Issued 5/10/2021 SERGIO MUNIZ
Plan Check Approved 11/16/2021 SERGIO MUNIZ
Issued 11/16/2021 APPLICANT
Building Plans Picked Up 11/17/2021 APPLICANT
CofO in Progress 3/2/2023 JENNIFER RABUCHIN
CofO Issued 3/7/2023 MICHAEL SMITH
Permit Finaled 3/7/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/18/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/18/2021 GABRIEL ROBLES
Sewer availability Cleared 5/18/2021 GABRIEL ROBLES
Low Impact Development Cleared 10/28/2021 JULIAN SUNG
Roof/Waste drainage to street Cleared 11/3/2021 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/19/2021 Conditional Approval RICHARD DOCKUS
Footing/Foundation/Slab 11/23/2021 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 11/24/2021 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 1/4/2022 Corrections Issued JENNIFER RABUCHIN
Gas Test 1/4/2022 Partial Approval JENNIFER RABUCHIN
Green Building Rough 1/4/2022 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/11/2022 Not Ready for Inspection DAVID MATSON
Green Building Rough 1/11/2022 Corrections Issued DAVID MATSON
Interior/Exterior Lathing 1/11/2022 Partial Approval DAVID MATSON
Rough-Elec/Plmb/HVAC 1/11/2022 Corrections Issued DAVID MATSON
Insulation 1/12/2022 Not Ready for Inspection ALAN MORELOS
Insulation 1/14/2022 Approved ALAN MORELOS
Drywall Nailing 1/19/2022 Conditional Approval ASHLEY THOMPSON
Interior/Exterior Lathing 1/19/2022 Partial Approval ASHLEY THOMPSON
Shower Pan 1/19/2022 Not Ready for Inspection ASHLEY THOMPSON
Interior/Exterior Lathing 1/20/2022 Approved ASHLEY THOMPSON
Shower Pan 1/20/2022 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 2/2/2023 Approved RYAN SALAZAR
Final 2/2/2023 Partial Inspection RYAN SALAZAR
Green Building Final 2/2/2023 Approved RYAN SALAZAR
Green Building Rough 2/2/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 2/2/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 2/2/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 3/1/2023 Approved JENNIFER RABUCHIN
Final 3/1/2023 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 3/1/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 3/1/2023 Approved JENNIFER RABUCHIN
Special/Order Compliance 3/1/2023 Approved JENNIFER RABUCHIN