5709 N MATILIJA AVE 91401
Certificate Information: 5709 N MATILIJA AVE 91401
- Application / Permit
- 21014-20000-01355
- Plan Check / Job No.
- B21VN03375
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 30'10" X 15'5" IRREGULAR SHAPED ADDITION TO (E) SFD TO CREATE (2) BEDROOMS , ENTRY , NEW 45'2" X 8' ADDITON TO (E) SFD TO ENLARGE KITCHEN AND (2) BEDROOMS , NEW 45'2" X 15'8" ATTACHED REAR COVERED PATIO , INTERIOR REMODEL TO (E) SFD TO REMODEL (3) BEDROOMS , KITCHEN , LIVING ROOM , (2) BATHROOM , CREATE BATHROOM AND LAUNDRY , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 7/19/2021
- Issuing Office
- Current Status
- CofO Issued on 4/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | RARES BODEA |
| Corrections Issued | 4/4/2021 | RARES BODEA |
| Quality Review Completed | 4/9/2021 | STEVEN KIM |
| Applicant returned to address corrections | 5/20/2021 | RARES BODEA |
| Plan Check Approved | 7/19/2021 | RARES BODEA |
| Issued | 7/19/2021 | APPLICANT |
| CofO in Progress | 4/7/2023 | RYAN SALAZAR |
| CofO Issued | 4/18/2023 | MICHAEL SMITH |
| Permit Finaled | 4/18/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/13/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 7/2/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 7/6/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Samadzadeh,, Hooman Ali; Lic. No.: C87661 | 22430 CRISWELL ST WEST HILLS, CA 91307 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/5/2021 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 12/1/2021 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 1/21/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 3/31/2022 | Partial Approval | RICHARD DOCKUS |
| Green Building Rough | 3/31/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 3/31/2022 | Corrections Issued | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2022 | Partial Approval | ALAN MORELOS |
| Green Building Rough | 4/6/2022 | No Access for Inspection | ALAN MORELOS |
| PLUMBING-Rough | 4/6/2022 | Partial Approval | ALAN MORELOS |
| BUILDING-Rough-Frame | 7/28/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 7/28/2022 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 7/28/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 7/28/2022 | Approved | JACK KARGODORIAN |
| Deputy Wood Construction | 8/3/2022 | Conditional Approval | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 8/19/2022 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Rough | 8/24/2022 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 8/24/2022 | Partial Approval | DEANDRE HOFFMAN |
| Insulation | 9/6/2022 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 9/12/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 9/27/2022 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 9/27/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/6/2023 | Approved | RYAN SALAZAR |
| Final | 4/6/2023 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 4/6/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 4/6/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 4/6/2023 | Approved | RYAN SALAZAR |