156 S VISTA ST 90036

Certificate Information: 156 S VISTA ST 90036

Application / Permit
21014-20000-01353
Plan Check / Job No.
B21VN03367
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND 1ST/2ND STORY ADDITION OF 67.7 SQFT TO (E) SFD
Permit Issued
Issued on 10/1/2021
Issuing Office
Current Status
CofO Issued on 6/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/22/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 PETER MOSESIAN
Corrections Issued 4/24/2021 PETER MOSESIAN
Quality Review Completed 5/6/2021 OMID HEDAYAT
Plan Check Approved 7/16/2021 PETER MOSESIAN
Issued 10/1/2021 APPLICANT
CofO in Progress 2/12/2024 LILIANA PORTILLO
CofO in Progress 2/12/2024 LILIANA PORTILLO
CofO Issued 6/14/2024 DEROLD HAUFF
Permit Finaled 6/14/2024 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 5/24/2021 LAUREN PADICK
HPOZ Cleared 6/25/2021 DANIEL MATA
Roof/Waste drainage to street Cleared 6/30/2021 WALLIE JONG
Sewer availability Cleared 6/30/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/6/2021 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Oruncakciel,, Sayat; Lic. No.: C77182 15445 VENTURA BLVD 25      SHERMAN OAKS, CA 91403

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 11/17/2022 Not Ready for Inspection MICHAEL LEWIS
HVAC-Rough 11/17/2022 Not Ready for Inspection MICHAEL LEWIS
METHANE-Rough 11/17/2022 Approved MICHAEL LEWIS
PLUMBING-Rough 11/17/2022 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 11/22/2022 Approved MICHAEL LEWIS
Shower Pan 11/22/2022 Approved MICHAEL LEWIS
Interior/Exterior Lathing 12/1/2022 Approved MICHAEL LEWIS
ELECTRICAL-Rough 12/7/2022 Approved MICHAEL LEWIS
HVAC-Rough 12/7/2022 Approved MICHAEL LEWIS
HVAC-Rough 12/9/2022 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 12/13/2022 Corrections Issued MICHAEL LEWIS
Green Building Rough 12/13/2022 Approved MICHAEL LEWIS
Insulation 12/13/2022 Partial Approval MICHAEL LEWIS
BUILDING-Rough-Frame 12/20/2022 Partial Inspection MICHAEL LEWIS
Insulation 12/20/2022 Partial Inspection MICHAEL LEWIS
BUILDING-Rough-Frame 1/5/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 1/5/2023 Approved MICHAEL LEWIS
Insulation 1/13/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 1/13/2023 Approved MICHAEL LEWIS
Drywall Nailing 1/17/2023 Approved MICHAEL LEWIS
Gas Test 3/30/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 4/28/2023 Corrections Issued LILIANA PORTILLO
Final 4/28/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 4/28/2023 Approved LILIANA PORTILLO
Green Building Final 4/28/2023 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 4/28/2023 Corrections Issued LILIANA PORTILLO
METHANE-Barrier 4/28/2023 Approved LILIANA PORTILLO
METHANE-Subgrade 4/28/2023 Approved LILIANA PORTILLO
PLUMBING-Final 4/28/2023 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 4/28/2023 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 4/28/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Final 2/9/2024 Approved LILIANA PORTILLO
Final 2/9/2024 OK to Issue CofO LILIANA PORTILLO
Green Building Final 2/9/2024 Approved LILIANA PORTILLO
HVAC-Final 2/9/2024 Approved LILIANA PORTILLO
Smoke Detectors 2/9/2024 Approved LILIANA PORTILLO