16736 W SUPERIOR ST 91343
Certificate Information: 16736 W SUPERIOR ST 91343
- Application / Permit
- 21014-20000-01339
- Plan Check / Job No.
- B21VN03313
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) SFD TO REMOVE HALLWAY, REMODEL (2) BATHROOMS/CLOSETS, RELOCATE KITCHEN, REFRAME ROOF, ADD 12' 6" X 4' ENTRY, ADD 48' X 45' 6" IRR.-SHAPE HABITABLE SPACE ADDITION ADD 20' X 7' PATIO COVER ADDITION TO REAR OF (E) SFD AND DEMOLISH ENCLOSURE IN REAR. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 11/21/2021
- Issuing Office
- Current Status
- CofO Issued on 10/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 4/17/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 10/19/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 11/5/2021 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 11/8/2021 | APPLICANT |
| Plan Check Approved | 11/21/2021 | GURUNATH NESARAJAH |
| Issued | 11/21/2021 | APPLICANT |
| CofO in Progress | 9/19/2022 | RAUL OLAGI |
| CofO Issued | 10/22/2022 | MICHAEL SMITH |
| Permit Finaled | 10/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Sewer availability | Cleared | 5/3/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 10/13/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 10/14/2021 | GABRIEL ROBLES |
| GPI Written Notices | Cleared | 10/19/2021 | GURUNATH NESARAJAH |
| Grading Pre-Inspection | Cleared | 10/19/2021 | GURUNATH NESARAJAH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazarians,, Harmick Edward; Lic. No.: C91232 | 9825 OSO AVE CHATSWORTH, CA 91311 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/12/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 1/18/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2022 | Partial Approval | MICHAEL TEMPLE |
| PLUMBING-Rough | 2/9/2022 | Corrections Issued | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2022 | Partial Approval | MICHAEL TEMPLE |
| PLUMBING-Rough | 2/11/2022 | Partial Approval | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2022 | Partial Approval | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 4/20/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 4/20/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 4/20/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 4/20/2022 | Approved | RAUL OLAGI |
| Deputy Wood Construction | 4/22/2022 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/4/2022 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2022 | Partial Approval | RAUL OLAGI |
| HVAC-Rough | 5/4/2022 | Approved | RAUL OLAGI |
| Shower Pan | 5/4/2022 | Approved | RAUL OLAGI |
| Deputy Drilled-In Anchors | 5/10/2022 | Conditional Approval | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 5/13/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 5/13/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/13/2022 | Partial Approval | RAUL OLAGI |
| Insulation | 5/23/2022 | Approved | ALAN MORELOS |
| Drywall Nailing | 5/27/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/27/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 8/22/2022 | Corrections Issued | RAUL OLAGI |
| Final | 8/22/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 8/22/2022 | Approved | RAUL OLAGI |
| HVAC-Final | 8/22/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 8/22/2022 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 8/22/2022 | SGSOV Not Ready | RAUL OLAGI |
| Smoke Detectors | 8/22/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 8/31/2022 | Not Ready for Inspection | RAUL OLAGI |
| Final | 8/31/2022 | No Access for Inspection | RAUL OLAGI |
| HVAC-Final | 8/31/2022 | No Access for Inspection | RAUL OLAGI |
| PLUMBING-Final | 8/31/2022 | No Access for Inspection | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 8/31/2022 | SGSOV Not Ready | RAUL OLAGI |
| ELECTRICAL-Final | 9/12/2022 | Approved | RAUL OLAGI |
| Final | 9/12/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 9/12/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 9/12/2022 | SGSOV Approved | RAUL OLAGI |
| Final | 9/19/2022 | OK to Issue CofO | RAUL OLAGI |