1824 N OLD ORCHARD ROAD 90049
Certificate Information: 1824 N OLD ORCHARD ROAD 90049
- Application / Permit
- 21014-20000-01338
- Plan Check / Job No.
- B21VN03296
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (N) TRELLIS (14'-9" X 12'-7") TO (E) 2-STORY SFD W/ ATTACHED GARAGE
- Permit Issued
- Issued on 6/28/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 3/29/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 5/4/2021 | NILOOFAR MEHRAIN |
| Issued | 6/28/2021 | APPLICANT |
| CofO in Progress | 7/19/2025 | MICHAEL PELHAM |
| Permit Finaled | 7/19/2025 | RICHARD STEINBACH |
| CofO Issued | 7/19/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/19/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/29/2021 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Paradigm Builders Inc; Lic. No.: 760924-B | 700 N SAN VICENTE BLVD G-410 LOS ANGELES, CA 90069 |
| Engineer | Garcia,, Lionel Jesus; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/30/2021 | Conditional Approval | ADAM ESCOTO |
| Excavation/Setback/Form/Re-Bar | 7/29/2021 | Approved | JUAN VALENZUELA |
| Gas Test | 7/29/2021 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 10/26/2021 | Approved | JUAN VALENZUELA |
| FLOOD-Elevation Certificate | 10/26/2021 | Approved | JUAN VALENZUELA |
| FLOOD-Proofing Certificate | 10/26/2021 | Approved | JUAN VALENZUELA |
| Final | 10/26/2021 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 10/26/2021 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 10/26/2021 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 10/26/2021 | Approved | JUAN VALENZUELA |
| Final | 7/19/2025 | OK to Issue CofO | MICHAEL PELHAM |