4231 S KENYON AVE 90066
Certificate Information: 4231 S KENYON AVE 90066
- Application / Permit
- 21014-20000-01336
- Plan Check / Job No.
- B21VN03284
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF (2) BEDROOMS, (2) FULL BATHROOMS, LIVING, DINING, LAUNDRY & POWDER ROOMS (IRR 60'-3" X 36'-8") AND ATTACHED PATIO COVER (8'-5" X5'-4"') TO (E) 1-STORY SFD W/ ATTACHED GARAGE; INTERIOR REMODEL (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 12/23/2021
- Issuing Office
- Current Status
- CofO Issued on 7/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 3/27/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 3/30/2021 | CHON CHIO KUO |
| Applicant returned to address corrections | 11/2/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 11/16/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 11/16/2021 | NILOOFAR MEHRAIN |
| No Progress | 12/20/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 12/20/2021 | NILOOFAR MEHRAIN |
| Issued | 12/23/2021 | APPLICANT |
| CofO in Progress | 7/27/2022 | HERBERT GIRON |
| CofO Issued | 7/28/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/28/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 6/24/2021 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 8/31/2021 | KURT CORRAL |
| Specific Plan | Cleared | 10/14/2021 | FREDDY GARCIA |
| Low Impact Development | Cleared | 11/18/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/29/2021 | ANTHONY MAINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/31/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2022 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 2/7/2022 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2022 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2022 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2022 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2022 | Conditional Approval | CLAYTON GRAHAM |
| PLUMBING-Rough | 3/1/2022 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 3/2/2022 | Conditional Approval | CLAYTON GRAHAM |
| HVAC-Rough | 3/2/2022 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 3/2/2022 | Conditional Approval | CLAYTON GRAHAM |
| Green Building Rough | 3/10/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 3/10/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Wood Frame | 3/10/2022 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 3/15/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 3/15/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 3/15/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 3/15/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/15/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 3/15/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 3/18/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Gas Test | 3/18/2022 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/30/2022 | Approved | JESUS RODRIGUEZ |
| Final | 6/30/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Final | 6/30/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 6/30/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 6/30/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 6/30/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 6/30/2022 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 6/30/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 7/26/2022 | Approved | HERBERT GIRON |
| Final | 7/26/2022 | OK to Issue CofO | HERBERT GIRON |
| Green Building Final | 7/26/2022 | Approved | HERBERT GIRON |
| Green Building Rough | 7/26/2022 | Approved | HERBERT GIRON |
| HVAC-Final | 7/26/2022 | Approved | HERBERT GIRON |