10649 W PAWNEE ST 91352
Certificate Information: 10649 W PAWNEE ST 91352
- Application / Permit
- 21014-20000-01335
- Plan Check / Job No.
- B21VN03282
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 14'-2" X 12'-8" ADDITION OF A WALK IN CLOSET TO THE (E) SFD. ALL WORK PER WFPP.
- Permit Issued
- Issued on 4/20/2021
- Issuing Office
- Current Status
- CofO Issued on 9/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2021 | PARISA ZAHABI |
| Corrections Issued | 3/22/2021 | PARISA ZAHABI |
| Plan Check Approved | 4/9/2021 | PARISA ZAHABI |
| Building Plans Picked Up | 4/9/2021 | APPLICANT |
| Issued | 4/20/2021 | APPLICANT |
| CofO in Progress | 8/10/2021 | WILLIAM KUEHN |
| Permit Finaled | 9/16/2021 | MICHAEL SMITH |
| CofO Issued | 9/16/2021 | MICHAEL SMITH |
| Permit Finaled | 9/16/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2021 | ABDULLAH SADOZAI |
| Roof/Waste drainage to street | Cleared | 3/24/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/29/2021 | Approved | BEAU COLLINS |
| Footing/Foundation/Slab | 4/29/2021 | Approved | BEAU COLLINS |
| Wood Frame | 5/6/2021 | Corrections Issued | JOHN HAYES |
| Wood Frame | 5/7/2021 | Partial Approval | JOHN HAYES |
| Wood Frame | 6/7/2021 | Partial Approval | DAVID MATSON |
| Wood Frame | 6/24/2021 | Partial Inspection | DAVID MATSON |
| BUILDING-Rough-Frame | 7/6/2021 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 7/6/2021 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 7/6/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/8/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 7/8/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 7/8/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 7/8/2021 | Approved | MATTHEW NELSON |
| MERV13>=Rough | 7/8/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 7/16/2021 | Partial Approval | GREGG CUMMINGS |
| Insulation | 7/20/2021 | Approved | ALAN MORELOS |
| Drywall Nailing | 7/26/2021 | Approved | ADAM ESCOTO |
| ELECTRICAL-Final | 8/9/2021 | Approved | WILLIAM KUEHN |
| Final | 8/9/2021 | OK to Issue CofO | WILLIAM KUEHN |
| Green Building Final | 8/9/2021 | Approved | WILLIAM KUEHN |
| HVAC-Final | 8/9/2021 | Approved | WILLIAM KUEHN |
| MERV13>=Final | 8/9/2021 | Approved | WILLIAM KUEHN |
| PLUMBING-Final | 8/9/2021 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 8/9/2021 | SGSOV Approved | WILLIAM KUEHN |
| Smoke Detectors | 8/9/2021 | Approved | WILLIAM KUEHN |