4173 N ELMER AVE 91602
Certificate Information: 4173 N ELMER AVE 91602
- Application / Permit
- 21014-20000-01334
- Plan Check / Job No.
- B21VN03279
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD (14'-7"x 8'-4") AT FIRST FLOOR AND CONVERT (E) DET GARAGE & ADD (13'-8'x 18'-3") AT 2ND STORY AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 3/31/2022
- Issuing Office
- Current Status
- CofO Issued on 2/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | TROY DEGUZMAN |
| Corrections Issued | 4/27/2021 | TROY DEGUZMAN |
| Quality Review Completed | 5/7/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 7/21/2021 | TROY DEGUZMAN |
| Applicant returned to address corrections | 8/12/2021 | TROY DEGUZMAN |
| Plan Check Approved | 3/31/2022 | TROY DEGUZMAN |
| Issued | 3/31/2022 | APPLICANT |
| CofO in Progress | 1/16/2024 | JOHN COLEMAN |
| Permit Finaled | 2/7/2024 | RUBEN SALAS |
| CofO Issued | 2/7/2024 | RUBEN SALAS |
| Permit Finaled | 2/7/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/26/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 7/27/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/28/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 8/30/2021 | SUNG JOON WON |
| Hydrant and Access approval | Cleared | 9/9/2021 | RUEL COLE |
| Roof/Waste drainage to street | Cleared | 9/9/2021 | DAGOVERTO GUERRERO |
| Green Code | Cleared | 9/24/2021 | TROY DEGUZMAN |
Contact Information
| Contractor | Schon Tepler Construction, Inc; Lic. No.: 969338-B | 6250 HOLLYWOOOD BLVD 10L LOS ANGELES, CA 90028 |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 214 ENCINO, CA 91342 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/14/2022 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 9/21/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Reinf. Concrete | 9/26/2022 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 11/18/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 11/18/2022 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2022 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 11/29/2022 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 11/29/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 11/29/2022 | Approved | JACK KARGODORIAN |
| Deputy Steel/Welding | 12/2/2022 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 3/8/2023 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 3/8/2023 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 3/8/2023 | Approved | JACK KARGODORIAN |
| Structural Steel Frame | 3/8/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 3/8/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/17/2023 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2023 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/17/2023 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2023 | Approved | JACK KARGODORIAN |
| Wood Frame | 3/20/2023 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Rough | 4/27/2023 | Partial Inspection | MICHEL ABAJAN |
| Insulation | 5/11/2023 | Corrections Issued | JACK KARGODORIAN |
| Insulation | 5/13/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Insulation | 5/19/2023 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 6/13/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 9/25/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Shower Pan | 9/25/2023 | Approved | THOMAS FINNILA |
| Wood Frame | 9/25/2023 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 9/27/2023 | Corrections Issued | JACK KARGODORIAN |
| Service/Power Release | 9/27/2023 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Final | 10/5/2023 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 10/5/2023 | Approved | MICHEL ABAJAN |
| Service/Power Release | 10/5/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/10/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 10/10/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/10/2023 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2023 | Approved | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 10/10/2023 | Approved | MISAEL ESPARZA |
| Service/Power Release | 10/10/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 10/10/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/16/2023 | Partial Approval | JOHN COLEMAN |
| PLUMBING-Final | 10/16/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Wood Frame | 10/16/2023 | Partial Approval | JOHN COLEMAN |
| ELECTRICAL-Final | 10/23/2023 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Final | 10/23/2023 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 10/30/2023 | Not Ready for Inspection | RUBEN SALAS |
| ELECTRICAL-Final | 10/30/2023 | Approved | RUBEN SALAS |
| Final | 10/30/2023 | Not Ready for Inspection | RUBEN SALAS |
| Footing/Foundation/Slab | 10/30/2023 | Not Ready for Inspection | RUBEN SALAS |
| Green Building Final | 10/30/2023 | Not Ready for Inspection | RUBEN SALAS |
| HVAC-Final | 10/30/2023 | Not Ready for Inspection | RUBEN SALAS |
| SGSOV-Seismic Gas S/O Valve | 10/30/2023 | SGSOV Not Ready | RUBEN SALAS |
| Smoke Detectors | 10/30/2023 | Not Ready for Inspection | RUBEN SALAS |
| Wood Frame | 10/30/2023 | Not Ready for Inspection | RUBEN SALAS |
| HVAC-Final | 11/14/2023 | Corrections Issued | JOHN COLEMAN |
| HVAC-Final | 11/20/2023 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 12/11/2023 | Corrections Issued | KIRK SANDERS |
| Final | 12/11/2023 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 12/11/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 12/11/2023 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/11/2023 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 12/11/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 1/10/2024 | Approved | JOHN COLEMAN |
| Final | 1/10/2024 | Corrections Issued | JOHN COLEMAN |
| Footing/Foundation/Slab | 1/10/2024 | Approved | JOHN COLEMAN |
| Green Building Final | 1/10/2024 | Corrections Issued | JOHN COLEMAN |
| Final | 1/16/2024 | OK to Issue CofO | JOHN COLEMAN |
| Green Building Final | 1/16/2024 | Approved | JOHN COLEMAN |
| Service/Power Release | 1/24/2024 | Approved | JOHN COLEMAN |