4171 N ELMER AVE 91602
Certificate Information: 4171 N ELMER AVE 91602
- Application / Permit
- 21014-20000-01333
- Plan Check / Job No.
- B21VN03279
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (56'-0"x 34'-3") IRR SHAPE MASTER BEDROOM WITH FULL BATH/ CLOSETS AND LIVING ROOM @ REAR PORTION OF (E) ONE-STORY SINGLE FAMILY DWELLING. WORK PER ENGINEER.
- Permit Issued
- Issued on 9/30/2021
- Issuing Office
- Current Status
- CofO Issued on 8/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | TROY DEGUZMAN |
| Corrections Issued | 4/27/2021 | TROY DEGUZMAN |
| Quality Review Completed | 5/7/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 7/21/2021 | TROY DEGUZMAN |
| Applicant returned to address corrections | 8/12/2021 | TROY DEGUZMAN |
| Plan Check Approved | 9/30/2021 | TROY DEGUZMAN |
| Issued | 9/30/2021 | APPLICANT |
| CofO in Progress | 8/5/2022 | THOMAS FINNILA |
| CofO in Progress | 8/5/2022 | THOMAS FINNILA |
| CofO Issued | 8/9/2022 | MICHAEL SMITH |
| Permit Finaled | 8/9/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 5/17/2021 | ADRIAN CASTRO |
| ZI | Cleared | 5/18/2021 | PABLO ESTRADA |
| Green Code | Cleared | 8/12/2021 | TROY DEGUZMAN |
| Low Impact Development | Cleared | 8/30/2021 | SUNG JOON WON |
| Hydrant and Access approval | Cleared | 9/9/2021 | RUEL COLE |
| Roof/Waste drainage to street | Cleared | 9/9/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Schon Tepler Construction, Inc; Lic. No.: 969338-B | 6250 HOLLYWOOOD BLVD 10L LOS ANGELES, CA 90028 |
| Engineer | Hoerner,, John Brent; Lic. No.: S2145 | 24024 VIA CANDELA VALENCIA, CA 91355 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/18/2021 | Partial Inspection | THOMAS FINNILA |
| Pre-Inspection | 10/18/2021 | Partial Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 10/22/2021 | Partial Inspection | THOMAS FINNILA |
| Deputy Reinf. Concrete | 10/26/2021 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 11/30/2021 | Partial Inspection | THOMAS FINNILA |
| Pre-Inspection | 12/7/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 1/21/2022 | Approved | MATT KELLERMAN |
| HVAC-Rough | 1/21/2022 | Approved | MATT KELLERMAN |
| Wood Frame | 1/21/2022 | Approved | MATT KELLERMAN |
| Interior/Exterior Lathing | 3/2/2022 | Approved | CALEB MEISTER |
| Insulation | 3/8/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 3/21/2022 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 3/21/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 4/12/2022 | Partial Approval | DAVID MATSON |
| PLUMBING-Rough | 4/12/2022 | Not Ready for Inspection | DAVID MATSON |
| ELECTRICAL-Final | 6/10/2022 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 6/16/2022 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/22/2022 | Approved | THOMAS FINNILA |
| Drywall Nailing | 6/22/2022 | Approved | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/22/2022 | Approved | THOMAS FINNILA |
| Final | 6/29/2022 | Corrections Issued | MATT KELLERMAN |
| Green Building Final | 6/29/2022 | Approved | MATT KELLERMAN |
| HVAC-Final | 6/29/2022 | Not Ready for Inspection | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 6/29/2022 | SGSOV No Gas | MATT KELLERMAN |
| Service/Power Release | 6/29/2022 | Approved | MATT KELLERMAN |
| Smoke Detectors | 6/29/2022 | Approved | MATT KELLERMAN |
| Deputy Reinf. Concrete | 7/6/2022 | Partial Approval | MATT KELLERMAN |
| ELECTRICAL-Final | 7/7/2022 | Corrections Issued | MATT KELLERMAN |
| Final | 7/7/2022 | Corrections Issued | MATT KELLERMAN |
| Gas Test | 7/7/2022 | Partial Inspection | JOHN KIDWELL |
| ELECTRICAL-Final | 7/25/2022 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 7/25/2022 | Approved | THOMAS FINNILA |
| Special/Order Compliance | 7/25/2022 | Partial Inspection | DAVID MATSON |
| Final | 8/4/2022 | OK to Issue CofO | THOMAS FINNILA |