4171 N ELMER AVE 91602

Certificate Information: 4171 N ELMER AVE 91602

Application / Permit
21014-20000-01333
Plan Check / Job No.
B21VN03279
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (56'-0"x 34'-3") IRR SHAPE MASTER BEDROOM WITH FULL BATH/ CLOSETS AND LIVING ROOM @ REAR PORTION OF (E) ONE-STORY SINGLE FAMILY DWELLING. WORK PER ENGINEER.
Permit Issued
Issued on 9/30/2021
Issuing Office
Current Status
CofO Issued on 8/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 TROY DEGUZMAN
Corrections Issued 4/27/2021 TROY DEGUZMAN
Quality Review Completed 5/7/2021 OMID HEDAYAT
Applicant returned to address corrections 7/21/2021 TROY DEGUZMAN
Applicant returned to address corrections 8/12/2021 TROY DEGUZMAN
Plan Check Approved 9/30/2021 TROY DEGUZMAN
Issued 9/30/2021 APPLICANT
CofO in Progress 8/5/2022 THOMAS FINNILA
CofO in Progress 8/5/2022 THOMAS FINNILA
CofO Issued 8/9/2022 MICHAEL SMITH
Permit Finaled 8/9/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/17/2021 ADRIAN CASTRO
Sewer availability Cleared 5/17/2021 ADRIAN CASTRO
ZI Cleared 5/18/2021 PABLO ESTRADA
Green Code Cleared 8/12/2021 TROY DEGUZMAN
Low Impact Development Cleared 8/30/2021 SUNG JOON WON
Hydrant and Access approval Cleared 9/9/2021 RUEL COLE
Roof/Waste drainage to street Cleared 9/9/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Schon Tepler Construction, Inc; Lic. No.: 969338-B 6250 HOLLYWOOOD BLVD 10L      LOS ANGELES, CA 90028
Engineer Hoerner,, John Brent; Lic. No.: S2145 24024 VIA CANDELA      VALENCIA, CA 91355

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/18/2021 Partial Inspection THOMAS FINNILA
Pre-Inspection 10/18/2021 Partial Inspection THOMAS FINNILA
Footing/Foundation/Slab 10/22/2021 Partial Inspection THOMAS FINNILA
Deputy Reinf. Concrete 10/26/2021 Approved MICHAEL PELHAM
BUILDING-Rough-Frame 11/30/2021 Partial Inspection THOMAS FINNILA
Pre-Inspection 12/7/2021 Approved THOMAS FINNILA
ELECTRICAL-Rough 1/21/2022 Approved MATT KELLERMAN
HVAC-Rough 1/21/2022 Approved MATT KELLERMAN
Wood Frame 1/21/2022 Approved MATT KELLERMAN
Interior/Exterior Lathing 3/2/2022 Approved CALEB MEISTER
Insulation 3/8/2022 Approved RYAN SALAZAR
Drywall Nailing 3/21/2022 Corrections Issued THOMAS FINNILA
Green Building Rough 3/21/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 4/12/2022 Partial Approval DAVID MATSON
PLUMBING-Rough 4/12/2022 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Final 6/10/2022 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 6/16/2022 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 6/22/2022 Approved THOMAS FINNILA
Drywall Nailing 6/22/2022 Approved THOMAS FINNILA
Footing/Foundation/Slab 6/22/2022 Approved THOMAS FINNILA
Final 6/29/2022 Corrections Issued MATT KELLERMAN
Green Building Final 6/29/2022 Approved MATT KELLERMAN
HVAC-Final 6/29/2022 Not Ready for Inspection MATT KELLERMAN
SGSOV-Seismic Gas S/O Valve 6/29/2022 SGSOV No Gas MATT KELLERMAN
Service/Power Release 6/29/2022 Approved MATT KELLERMAN
Smoke Detectors 6/29/2022 Approved MATT KELLERMAN
Deputy Reinf. Concrete 7/6/2022 Partial Approval MATT KELLERMAN
ELECTRICAL-Final 7/7/2022 Corrections Issued MATT KELLERMAN
Final 7/7/2022 Corrections Issued MATT KELLERMAN
Gas Test 7/7/2022 Partial Inspection JOHN KIDWELL
ELECTRICAL-Final 7/25/2022 Approved THOMAS FINNILA
PLUMBING-Final 7/25/2022 Approved THOMAS FINNILA
Special/Order Compliance 7/25/2022 Partial Inspection DAVID MATSON
Final 8/4/2022 OK to Issue CofO THOMAS FINNILA