15441 W ROMAR ST 91345

Certificate Information: 15441 W ROMAR ST 91345

Application / Permit
21014-20000-01324
Plan Check / Job No.
B21VN03255
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
424.5 SQFT ADDITION TO THE (E) SFD AND REMOVE (E) PATIO COVER. ALL WORK PER WFPP.
Permit Issued
Issued on 10/5/2021
Issuing Office
Current Status
CofO Issued on 1/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2021 APPLICANT
Assigned to Plan Check Engineer 3/22/2021 JESSE ARELLANO
Corrections Issued 3/22/2021 JESSE ARELLANO
Applicant returned to address corrections 9/1/2021 JESSE ARELLANO
Applicant returned to address corrections 9/20/2021 LUISANGEL VALENZUELA
Applicant returned to address corrections 9/29/2021 LUISANGEL VALENZUELA
Issued 10/5/2021 APPLICANT
Building Plans Picked Up 10/6/2021 APPLICANT
CofO in Progress 1/20/2022 JENNIFER RABUCHIN
Permit Finaled 1/22/2022 MICHAEL SMITH
CofO Issued 1/22/2022 MICHAEL SMITH
Permit Finaled 1/22/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/31/2021 GABRIEL ROBLES
Sewer availability Cleared 3/31/2021 GABRIEL ROBLES
Green Code Cleared 9/28/2021 JESSE ARELLANO
Roof/Waste drainage to street Cleared 9/30/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/12/2021 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 10/18/2021 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/27/2021 Partial Approval JENNIFER RABUCHIN
Green Building Rough 10/27/2021 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 10/27/2021 Partial Approval JENNIFER RABUCHIN
MERV13>=Rough 10/27/2021 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/2/2021 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 11/2/2021 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 11/2/2021 Approved JENNIFER RABUCHIN
Green Building Rough 11/2/2021 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 11/2/2021 Approved JENNIFER RABUCHIN
Insulation 11/5/2021 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 11/5/2021 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 11/9/2021 Approved JENNIFER RABUCHIN
HVAC-Rough 11/9/2021 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/20/2021 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 12/20/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Final 12/20/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 12/20/2021 Approved CHRISTOPHER DELLEFIELD
Green Building Final 12/20/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Rough 12/20/2021 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 12/20/2021 Corrections Issued CHRISTOPHER DELLEFIELD
MERV13>=Final 12/20/2021 Corrections Issued CHRISTOPHER DELLEFIELD
MERV13>=Rough 12/20/2021 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 12/20/2021 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 12/20/2021 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 1/10/2022 Corrections Issued MICHEL ABAJAN
Final 1/10/2022 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 1/10/2022 Approved MICHEL ABAJAN
HVAC-Final 1/10/2022 Not Ready for Inspection MICHEL ABAJAN
MERV13>=Final 1/10/2022 Approved MICHEL ABAJAN
PLUMBING-Final 1/10/2022 Approved MICHEL ABAJAN
Smoke Detectors 1/10/2022 Approved MICHEL ABAJAN
Final 1/12/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 1/20/2022 Approved JENNIFER RABUCHIN
Final 1/20/2022 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 1/20/2022 Approved JENNIFER RABUCHIN
PLUMBING-Final 1/20/2022 Approved JENNIFER RABUCHIN