231 E 91ST ST 90003

Certificate Information: 231 E 91ST ST 90003

Application / Permit
21014-20000-01311
Plan Check / Job No.
B21VN03221
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SFD IRR. SHAPE (24'-1"x26'-0") of 373 sq-ft
Permit Issued
Issued on 11/3/2021
Issuing Office
Current Status
Issued on 11/3/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/18/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 MOHAMMAD ESMAILI
Corrections Issued 4/27/2021 MOHAMMAD ESMAILI
Quality Review Completed 5/7/2021 OMID HEDAYAT
Applicant returned to address corrections 10/27/2021 MOHAMMAD ESMAILI
Plan Check Approved 11/3/2021 MOHAMMAD ESMAILI
Issued 11/3/2021 APPLICANT

Permit Application Clearance Information

Low Impact Development Cleared 10/4/2021 CHRIS VONG
Miscellaneous Cleared 10/7/2021 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 10/7/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 10/8/2021 CECILIO NAVARRO
Sewer availability Cleared 10/14/2021 CECILIO NAVARRO

Contact Information

Contractor Aldan Construction & Remodeling Inc; Lic. No.: 1030243-B 8549 WILSHIRE BLVD #1458      BEVERLY HILLS, CA 90211
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/12/2021 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 11/22/2021 Corrections Issued ADAM ESCOTO
Footing/Foundation/Slab 11/22/2021 Conditional Approval ADAM ESCOTO
BUILDING-Rough-Frame 12/7/2021 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 12/7/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/7/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/13/2021 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 12/16/2021 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 12/16/2021 Not Ready for Inspection ALEJANDRO DE ARTOLA
Wood Frame 12/16/2021 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/3/2022 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 1/3/2022 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/4/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/4/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/1/2022 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 2/10/2022 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 2/10/2022 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 2/10/2022 Approved ALIZAH MAYAGOITIA
Green Building Rough 2/10/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 2/10/2022 Approved ALIZAH MAYAGOITIA
Insulation 2/10/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 2/10/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 2/22/2022 Approved LILIANA PORTILLO
Green Building Rough 2/22/2022 Approved LILIANA PORTILLO
Insulation 2/22/2022 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 2/22/2022 Approved LILIANA PORTILLO
Drywall Nailing 3/7/2022 Corrections Issued LILIANA PORTILLO
Drywall Nailing 3/14/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 4/19/2022 Approved LILIANA PORTILLO
Final 4/19/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 4/19/2022 Approved LILIANA PORTILLO
Green Building Final 4/19/2022 Corrections Issued LILIANA PORTILLO
HVAC-Final 4/19/2022 Approved LILIANA PORTILLO
PLUMBING-Final 4/19/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 4/19/2022 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 4/19/2022 Approved LILIANA PORTILLO