15110 W HARTSOOK ST 91403

Certificate Information: 15110 W HARTSOOK ST 91403

Application / Permit
21014-20000-01274
Plan Check / Job No.
B21VN03153
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 36'6" X 35' 2ND FLOOR ADDITION TO (E) SFD TO CREATE (3) BEDROOMS , (2) BATHROOMS , W.I.C. , INTERIOR REMODEL TO (E) SFD TO CONVERT (2) BEDROOMS INTO LIVING ROOM , REMODEL DINING ROOM AND FAMILY ROOM , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT , ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/26/2022
Issuing Office
Current Status
CofO Issued on 3/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 RARES BODEA
Corrections Issued 4/18/2021 RARES BODEA
Quality Review Completed 4/29/2021 STEVEN KIM
Applicant returned to address corrections 1/5/2022 RARES BODEA
Plan Check Approved 1/21/2022 RARES BODEA
Issued 1/26/2022 APPLICANT
CofO in Progress 1/23/2024 DAVID ANDERSON
Permit Finaled 3/21/2024 RUBEN SALAS
CofO Issued 3/21/2024 RUBEN SALAS
Permit Finaled 3/21/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/26/2021 ADRIAN CASTRO
Sewer availability Cleared 5/26/2021 ADRIAN CASTRO
Low Impact Development Cleared 10/1/2021 CHRIS VONG
Roof/Waste drainage to street Cleared 1/7/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/8/2022 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 5/3/2022 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 6/1/2022 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 8/9/2022 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 8/9/2022 Not Ready for Inspection JACK KARGODORIAN
Deputy Drilled-In Anchors 8/19/2022 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 8/23/2022 Partial Approval CALEB MEISTER
PLUMBING-Rough 10/6/2022 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 10/11/2022 No Access for Inspection THOMAS FINNILA
ELECTRICAL-Rough 10/17/2022 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 10/17/2022 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 10/20/2022 Corrections Issued THOMAS FINNILA
HVAC-Rough 10/20/2022 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 11/1/2022 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 11/1/2022 Approved THOMAS FINNILA
PLUMBING-Rough 11/1/2022 Approved THOMAS FINNILA
BUILDING-Rough-Frame 11/16/2022 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 11/16/2022 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 11/16/2022 Approved THOMAS FINNILA
Deputy Wood Construction 11/18/2022 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 1/18/2023 No Access for Inspection THOMAS FINNILA
Piling/Pier/Caisson 1/20/2023 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 1/25/2023 Approved THOMAS FINNILA
BUILDING-Rough-Frame 2/2/2023 Approved MATTHEW NELSON
Green Building Rough 2/2/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 2/24/2023 No Access for Inspection THOMAS FINNILA
Interior/Exterior Lathing 3/6/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/7/2023 No Access for Inspection JOHN COLEMAN
Insulation 3/9/2023 Corrections Issued JOHN COLEMAN
Insulation 3/28/2023 Conditional Approval THOMAS FINNILA
Drywall Nailing 3/31/2023 Approved DAVID MATSON
Interior/Exterior Lathing 4/14/2023 Not Ready for Inspection THOMAS FINNILA
Shower Pan 4/14/2023 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 4/19/2023 Approved THOMAS FINNILA
Shower Pan 4/19/2023 Approved THOMAS FINNILA
Final 12/8/2023 Corrections Issued THOMAS FINNILA
Green Building Final 12/8/2023 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 12/8/2023 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 12/8/2023 Not Ready for Inspection THOMAS FINNILA
Final 1/12/2024 Corrections Issued THOMAS FINNILA
Green Building Final 1/12/2024 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 1/12/2024 SGSOV Approved THOMAS FINNILA
Smoke Detectors 1/12/2024 Approved THOMAS FINNILA
Final 1/22/2024 OK to Issue CofO DAVID ANDERSON