11845 W OXNARD ST 91606
Certificate Information: 11845 W OXNARD ST 91606
- Application / Permit
- 21014-20000-01273
- Plan Check / Job No.
- B21VN03152
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ECPC: 10 X 17 ADDITION TO AND CONVERT (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g); ALL WORK PER WFPP
- Permit Issued
- Issued on 7/13/2021
- Issuing Office
- Current Status
- CofO Issued on 10/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | SEAN SHAHMIRI |
| Corrections Issued | 3/28/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 7/8/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 7/9/2021 | SEAN SHAHMIRI |
| Issued | 7/13/2021 | APPLICANT |
| CofO in Progress | 10/26/2021 | MICHAEL PELHAM |
| Permit Finaled | 10/26/2021 | MICHAEL SMITH |
| CofO Issued | 10/26/2021 | MICHAEL SMITH |
| Permit Finaled | 10/26/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/8/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 4/8/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 6/26/2021 | RIDWAN HARDY |
| Sewer availability | Cleared | 6/30/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Ultimate Green Construction Inc; Lic. No.: 1023605-B | 13302 FILMORE ST PACOIMA, CA 91331 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/22/2021 | Conditional Approval | DANIEL DREW |
| Footing/Foundation/Slab | 7/26/2021 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 8/19/2021 | Approved | DANIEL DREW |
| Gas Test | 8/19/2021 | Not Ready for Inspection | DANIEL DREW |
| HVAC-Rough | 8/19/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 8/19/2021 | Approved | DANIEL DREW |
| Wood Frame | 8/19/2021 | Approved | DANIEL DREW |
| Insulation | 8/25/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 8/25/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2021 | Approved | DANIEL DREW |
| Drywall Nailing | 9/7/2021 | Approved | DANIEL DREW |
| Green Building Rough | 9/7/2021 | Approved | DANIEL DREW |
| Underground Mechanical | 9/23/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Underground Mechanical | 10/5/2021 | Not Ready for Inspection | CALEB MEISTER |
| Underground Mechanical | 10/6/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 10/19/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 10/19/2021 | Approved | DANIEL DREW |
| Final | 10/19/2021 | Corrections Issued | DANIEL DREW |
| Green Building Final | 10/19/2021 | Approved | DANIEL DREW |
| HVAC-Final | 10/19/2021 | Approved | DANIEL DREW |
| MERV13>=Final | 10/19/2021 | Approved | DANIEL DREW |
| MERV13>=Rough | 10/19/2021 | Approved | DANIEL DREW |
| PLUMBING-Final | 10/19/2021 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 10/19/2021 | SGSOV Approved | DANIEL DREW |
| Smoke Detectors | 10/19/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 10/22/2021 | Approved | DANIEL DREW |
| Final | 10/22/2021 | OK to Issue CofO | DANIEL DREW |
| HVAC-Final | 10/22/2021 | Approved | DANIEL DREW |
| PLUMBING-Final | 10/22/2021 | Approved | DANIEL DREW |
| Service/Power Release | 10/22/2021 | Approved | DANIEL DREW |