- Permit Issued
- Issued on 6/14/2021
- Issuing Office
- Current Status
- CofO Issued on 12/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2021 | PARISA ZAHABI |
| Corrections Issued | 3/24/2021 | PARISA ZAHABI |
| Plan Check Approved | 5/27/2021 | PARISA ZAHABI |
| Building Plans Picked Up | 6/1/2021 | APPLICANT |
| Issued | 6/14/2021 | APPLICANT |
| CofO in Progress | 12/1/2021 | STUART CHAPMAN |
| Permit Finaled | 12/15/2021 | DEROLD HAUFF |
| CofO Issued | 12/15/2021 | DEROLD HAUFF |
| Permit Finaled | 12/15/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/7/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 4/7/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 4/7/2021 | RENZ SORIANO |
| Construction near power lines | Cleared | 5/17/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2021 | RENZ SORIANO |
Contact Information
| Contractor | So Cal Construction Enterprises Inc; Lic. No.: 832488-B | P O BOX 96 SAN GABRIEL, CA 91778 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/18/2021 | Approved | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 7/2/2021 | Partial Approval | RONALD KIDWELL |
| Footing/Foundation/Slab | 7/2/2021 | Approved | RUBEN SALAS |
| Underground Mechanical | 7/2/2021 | Partial Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 7/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 7/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 7/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 7/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 7/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 7/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 7/19/2021 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 7/19/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 7/21/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Sewer | 7/28/2021 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 8/10/2021 | Approved | STUART CHAPMAN |
| Final | 8/10/2021 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 8/10/2021 | Approved | STUART CHAPMAN |
| HVAC-Final | 8/10/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 8/10/2021 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 8/10/2021 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 8/10/2021 | Approved | STUART CHAPMAN |
| Smoke Detectors | 8/10/2021 | Approved | STUART CHAPMAN |
| Final | 12/1/2021 | OK to Issue CofO | STUART CHAPMAN |
| Special/Order Compliance | 12/11/2021 | Approved | STUART CHAPMAN |