4742 N RONMAR PL 91364

Certificate Information: 4742 N RONMAR PL 91364

Application / Permit
21014-20000-01265
Plan Check / Job No.
B21VN03111
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION L-SHAPED ( 48'-1" X 25'-8" ) TO (E) SFD FOR NEW BEDROOM/ BATHROOM/ CLOSET. INTERIOR REMODEL TO (E) BEDROOMS/ DINING AND ROOM LIVING ROOM. WORK PER ENGINEER.
Permit Issued
Issued on 2/7/2022
Issuing Office
Current Status
CofO Issued on 8/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 RICHARD GARCIA
Corrections Issued 3/31/2021 RICHARD GARCIA
Applicant returned to address corrections 11/2/2021 ROSENDO MEDINA
Building Plans Picked Up 11/3/2021 APPLICANT
Plan Check Approved 2/4/2022 MOHAMMAD ESMAILI
Plan Check Approved 2/4/2022 MOHAMMAD ESMAILI
Issued 2/7/2022 APPLICANT
CofO in Progress 12/26/2024 JOHN HAYES
Permit Finaled 8/22/2025 JOHN JANSON
CofO Issued 8/22/2025 JOHN JANSON
Permit Finaled 8/22/2025 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/30/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 4/30/2021 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 5/3/2021 BRIAN MILLER
ZI Cleared 5/10/2021 PABLO ESTRADA
Low Impact Development Cleared 11/3/2021 RICHARD GARCIA
Roof/Waste drainage to street Cleared 11/4/2021 JOSE DUARTE-DIAZ
Hydrant and Access approval Cleared 1/29/2022 RUEL COLE
GPI Written Notices Cleared 2/4/2022 RICHARD GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/22/2022 Corrections Issued PETER FOLLING
Excavation/Setback/Form/Re-Bar 2/28/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 3/17/2022 Partial Approval PETER FOLLING
PLUMBING-Rough 3/17/2022 Partial Approval PETER FOLLING
BUILDING-Rough-Frame 3/29/2022 Partial Approval PETER FOLLING
Insulation 3/29/2022 Partial Approval PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 6/3/2022 Partial Approval PETER FOLLING
Wood Frame 6/3/2022 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Rough 6/28/2022 Approved PETER FOLLING
HVAC-Rough 7/8/2022 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 7/8/2022 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Approved PETER FOLLING
Green Building Rough 8/15/2022 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 8/19/2022 Approved PETER FOLLING
Green Building Rough 8/19/2022 Approved PETER FOLLING
Interior/Exterior Lathing 8/19/2022 Partial Approval PETER FOLLING
Insulation 8/24/2022 Approved PETER FOLLING
Drywall Nailing 9/1/2022 Approved PETER FOLLING
Shower Pan 9/23/2022 Corrections Issued JUSTIN HAWLEY
Interior/Exterior Lathing 9/28/2022 Not Ready for Inspection JESUS PINEDA
Shower Pan 9/28/2022 Approved JESUS PINEDA
Final 1/10/2024 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 1/10/2024 Approved JOHN KIDWELL
Green Building Final 1/10/2024 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 1/10/2024 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 1/10/2024 Approved JOHN KIDWELL
ELECTRICAL-Final 2/2/2024 Approved JOHN KIDWELL
Green Building Final 2/2/2024 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 2/2/2024 SGSOV Approved JOHN KIDWELL
Final 12/26/2024 OK to Issue CofO JOHN HAYES
Special/Order Compliance 12/31/2024 Corrections Issued SEAN WIRCH
Pre-Inspection 1/7/2025 Approved JOHN HAYES