6817 N BERTRAND AVE 91335

Certificate Information: 6817 N BERTRAND AVE 91335

Application / Permit
21014-20000-01263
Plan Check / Job No.
B21VN03108
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 36'-3" X 21'-6" TWO STORY ACCESSORY DWELLING UNIT TO EXISTING DETACHED GARAGE PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 1/13/2022
Issuing Office
Current Status
CofO Issued on 4/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 SELLA BENYAMIN
Corrections Issued 4/20/2021 SELLA BENYAMIN
Quality Review Completed 4/23/2021 STEVEN KIM
Plan Check Approved 1/7/2022 SELLA BENYAMIN
Issued 1/13/2022 APPLICANT
CofO in Progress 3/29/2023 JEFFREY BULL
Permit Finaled 4/13/2023 JOHN JANSON
CofO Issued 4/13/2023 JOHN JANSON
Permit Finaled 4/13/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/26/2021 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 5/5/2021 GUILLERMO PETRA
Sewer availability Cleared 5/5/2021 GUILLERMO PETRA
Hydrant and Access approval Cleared 7/6/2021 KURT CORRAL
Low Impact Development Cleared 10/21/2021 TA ANH
Roof/Waste drainage to street Cleared 10/22/2021 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/3/2022 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 3/9/2022 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 3/9/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 3/9/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/25/2022 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 8/31/2022 Approved JEFFREY BULL
ELECTRICAL-Rough 8/31/2022 Approved JEFFREY BULL
Green Building Rough 8/31/2022 Approved JEFFREY BULL
HVAC-Rough 8/31/2022 Approved JEFFREY BULL
PLUMBING-Rough 8/31/2022 Approved JEFFREY BULL
Insulation 9/20/2022 Approved JEFFREY BULL
Interior/Exterior Lathing 9/20/2022 Approved JEFFREY BULL
Drywall Nailing 10/3/2022 Approved JEFFREY BULL
Interior/Exterior Lathing 10/3/2022 Approved JEFFREY BULL
Shower Pan 10/3/2022 Approved JEFFREY BULL
Underground Mechanical 12/23/2022 Partial Approval JEFFREY BULL
Final 3/21/2023 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 3/21/2023 Approved CHRIS CHRISTENSEN
Green Building Final 3/21/2023 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 3/21/2023 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 3/21/2023 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 3/28/2023 Approved JEFFREY BULL
Final 3/28/2023 OK to Issue CofO JEFFREY BULL
Green Building Final 3/28/2023 Approved JEFFREY BULL
HVAC-Final 3/28/2023 Approved JEFFREY BULL
PLUMBING-Final 3/28/2023 Approved JEFFREY BULL