20911 W DUMETZ ROAD 91364

Certificate Information: 20911 W DUMETZ ROAD 91364

Application / Permit
21014-20000-01262
Plan Check / Job No.
B21VN03105
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 8'6" X 40'5" ADDITION TO (E) SFD TO ENLARGE (3) BEDROOMS AND (1) BATHROOM, CREATE (1) BATHROOM , NEW 8' X 9'5" AND 14'6" X 6'6" OPEN TRELLISES , MAJOR REMODEL TO (E) SFD TO RE-FRAME ALL THE ROOF , REMODEL (3) BEDROOMS , (1) BATHROOM , LIVING ROOM , KITCHEN , CREATE NEW LAUNDRY , DOORS AND WINDOWS CHANGEOUT, NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING
Permit Issued
Issued on 11/4/2021
Issuing Office
Current Status
CofO Issued on 12/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 RARES BODEA
Corrections Issued 3/27/2021 RARES BODEA
Quality Review Completed 4/5/2021 STEVEN KIM
Applicant returned to address corrections 9/20/2021 RARES BODEA
Applicant returned to address corrections 11/2/2021 RARES BODEA
Plan Check Approved 11/4/2021 RARES BODEA
Issued 11/4/2021 APPLICANT
CofO in Progress 11/8/2022 PETER FOLLING
Permit Finaled 12/9/2022 MICHAEL SMITH
CofO Issued 12/9/2022 MICHAEL SMITH
Permit Finaled 12/9/2022 MICHAEL SMITH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 6/15/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 6/15/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 6/15/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 6/15/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 6/15/2021 CARLOS AGUILERA
Sewer availability Cleared 6/15/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/16/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 9/11/2021 MATTHEW CRAIG
Distance to fire station Cleared 9/21/2021 MATTHEW CRAIG
Low Impact Development Cleared 10/7/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 10/7/2021 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 11/4/2021 RARES BODEA

Contact Information

Architect Ryder,, Eric Otto; Lic. No.: C32173 2004 19TH STREET      SANTA MONICA, CA 90404
Contractor Salles Construction Inc; Lic. No.: 859735-B 12792 VALLEY VIEW ST #206      GARDEN GROVE, CA 92845
Engineer Cosentino,, Joseph; Lic. No.: C53176 820 ISABELLA      MONTEREY PARK, CA 91754

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/9/2021 No Access for Inspection PETER FOLLING
Footing/Foundation/Slab 11/10/2021 Corrections Issued PETER FOLLING
Footing/Foundation/Slab 11/19/2021 Approved PETER FOLLING
BUILDING-Rough-Frame 12/9/2021 Partial Approval VINCENT HANLEY
Green Building Rough 12/9/2021 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 12/9/2021 Partial Approval VINCENT HANLEY
Verify Sprinkler Sign Off 12/9/2021 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 12/17/2021 Partial Approval PETER FOLLING
Deputy Drilled-In Anchors 2/24/2022 Conditional Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 2/28/2022 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Rough 2/28/2022 Not Ready for Inspection PETER FOLLING
Green Building Rough 2/28/2022 Not Ready for Inspection PETER FOLLING
HVAC-Rough 2/28/2022 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 2/28/2022 Approved PETER FOLLING
Verify Sprinkler Sign Off 2/28/2022 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 3/8/2022 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Rough 3/8/2022 Approved PETER FOLLING
Green Building Rough 3/8/2022 Not Ready for Inspection PETER FOLLING
HVAC-Rough 3/8/2022 Approved PETER FOLLING
PLUMBING-Rough 3/8/2022 Approved PETER FOLLING
Verify Sprinkler Sign Off 3/8/2022 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 5/12/2022 Approved PETER FOLLING
Green Building Rough 5/12/2022 Approved PETER FOLLING
Insulation 5/12/2022 Approved PETER FOLLING
Interior/Exterior Lathing 5/12/2022 Partial Approval PETER FOLLING
Shower Pan 5/12/2022 Approved PETER FOLLING
Verify Sprinkler Sign Off 5/12/2022 Approved PETER FOLLING
Drywall Nailing 5/18/2022 Approved PETER FOLLING
Interior/Exterior Lathing 6/27/2022 Approved PETER FOLLING
Final 10/20/2022 Corrections Issued PETER FOLLING
Green Building Final 10/20/2022 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 10/20/2022 SGSOV Not Ready PETER FOLLING
Smoke Detectors 10/20/2022 Approved PETER FOLLING
Final 11/7/2022 OK to Issue CofO PETER FOLLING
SGSOV-Seismic Gas S/O Valve 11/7/2022 SGSOV Approved PETER FOLLING