7656 N SHADYGLADE AVE 91605
Certificate Information: 7656 N SHADYGLADE AVE 91605
- Application / Permit
- 21014-20000-01258
- Plan Check / Job No.
- B21VN03092
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 9'-6" x 18'-1" TO THE FRONT AND 16'-11" x 19'-0" TO REAR (453.6 SF IN TOTAL) TO (E) SINGLE FAMILY DWELLING AND INTERIOR REMODEL; ALL WORK PER ENGINEERING DESIGN;
- Permit Issued
- Issued on 6/9/2021
- Issuing Office
- Current Status
- CofO Issued on 3/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | SEAN SHAHMIRI |
| Corrections Issued | 3/28/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 5/18/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 6/9/2021 | SEAN SHAHMIRI |
| Issued | 6/9/2021 | APPLICANT |
| CofO in Progress | 2/7/2022 | CHRISTOPHER DELLEFIELD |
| CofO Issued | 3/5/2022 | MICHAEL SMITH |
| Permit Finaled | 3/5/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/5/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 6/4/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/14/2021 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 6/14/2021 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 6/14/2021 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 7/2/2021 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 7/2/2021 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 7/7/2021 | Approved | JOHN HAYES |
| Wood Frame | 7/7/2021 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 8/18/2021 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 8/18/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 8/18/2021 | Not Ready for Inspection | JOHN HAYES |
| METHANE-Rough | 8/18/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 8/18/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 8/30/2021 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 8/30/2021 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2021 | Partial Approval | JOHN HAYES |
| Green Building Rough | 8/30/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 8/30/2021 | Not Ready for Inspection | JOHN HAYES |
| METHANE-Rough | 8/30/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 8/30/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 9/3/2021 | Approved | JOHN HAYES |
| Green Building Rough | 9/3/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 9/3/2021 | Partial Approval | JOHN HAYES |
| METHANE-Rough | 9/3/2021 | Approved | JOHN HAYES |
| PLUMBING-Rough | 9/3/2021 | Approved | JOHN HAYES |
| Insulation | 9/9/2021 | Approved | JOHN HAYES |
| Drywall Nailing | 9/14/2021 | Approved | JUSTIN HAWLEY |
| Shower Pan | 9/22/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 1/12/2022 | Partial Inspection | GREGG CUMMINGS |
| Green Building Final | 1/12/2022 | Partial Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/12/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 1/12/2022 | Partial Inspection | GREGG CUMMINGS |
| Final | 1/20/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 1/20/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 1/20/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 1/20/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 2/1/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 2/1/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 2/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 2/1/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 2/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 2/1/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 2/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 2/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 2/7/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 2/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 2/7/2022 | Approved | CHRISTOPHER DELLEFIELD |