7656 N SHADYGLADE AVE 91605

Certificate Information: 7656 N SHADYGLADE AVE 91605

Application / Permit
21014-20000-01258
Plan Check / Job No.
B21VN03092
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 9'-6" x 18'-1" TO THE FRONT AND 16'-11" x 19'-0" TO REAR (453.6 SF IN TOTAL) TO (E) SINGLE FAMILY DWELLING AND INTERIOR REMODEL; ALL WORK PER ENGINEERING DESIGN;
Permit Issued
Issued on 6/9/2021
Issuing Office
Current Status
CofO Issued on 3/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 SEAN SHAHMIRI
Corrections Issued 3/28/2021 SEAN SHAHMIRI
Applicant returned to address corrections 5/18/2021 SEAN SHAHMIRI
Plan Check Approved 6/9/2021 SEAN SHAHMIRI
Issued 6/9/2021 APPLICANT
CofO in Progress 2/7/2022 CHRISTOPHER DELLEFIELD
CofO Issued 3/5/2022 MICHAEL SMITH
Permit Finaled 3/5/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/5/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 4/5/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 6/4/2021 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/14/2021 Approved MICHEL ABAJAN
METHANE-Barrier 6/14/2021 Approved MICHEL ABAJAN
METHANE-Subgrade 6/14/2021 Approved MICHEL ABAJAN
Underground Mechanical 7/2/2021 Not Ready for Inspection JOHN HAYES
Wood Frame 7/2/2021 Corrections Issued JOHN HAYES
Underground Mechanical 7/7/2021 Approved JOHN HAYES
Wood Frame 7/7/2021 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 7/19/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 8/18/2021 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 8/18/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 8/18/2021 Not Ready for Inspection JOHN HAYES
METHANE-Rough 8/18/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 8/18/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 8/30/2021 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 8/30/2021 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 8/30/2021 Partial Approval JOHN HAYES
Green Building Rough 8/30/2021 Not Ready for Inspection JOHN HAYES
HVAC-Rough 8/30/2021 Not Ready for Inspection JOHN HAYES
METHANE-Rough 8/30/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 8/30/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 9/3/2021 Approved JOHN HAYES
Green Building Rough 9/3/2021 Approved JOHN HAYES
Interior/Exterior Lathing 9/3/2021 Partial Approval JOHN HAYES
METHANE-Rough 9/3/2021 Approved JOHN HAYES
PLUMBING-Rough 9/3/2021 Approved JOHN HAYES
Insulation 9/9/2021 Approved JOHN HAYES
Drywall Nailing 9/14/2021 Approved JUSTIN HAWLEY
Shower Pan 9/22/2021 Approved CHRISTOPHER DELLEFIELD
Final 1/12/2022 Partial Inspection GREGG CUMMINGS
Green Building Final 1/12/2022 Partial Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 1/12/2022 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 1/12/2022 Partial Inspection GREGG CUMMINGS
Final 1/20/2022 Corrections Issued JOHN HAYES
Green Building Final 1/20/2022 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 1/20/2022 SGSOV Not Ready JOHN HAYES
Smoke Detectors 1/20/2022 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 2/1/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 2/1/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 2/1/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 2/1/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 2/1/2022 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 2/1/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 2/1/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 2/7/2022 Approved CHRISTOPHER DELLEFIELD
Final 2/7/2022 OK to Issue CofO CHRISTOPHER DELLEFIELD
HVAC-Final 2/7/2022 Approved CHRISTOPHER DELLEFIELD
Service/Power Release 2/7/2022 Approved CHRISTOPHER DELLEFIELD