3842 S SOMERSET DR 90008
Certificate Information: 3842 S SOMERSET DR 90008
- Application / Permit
- 21014-20000-01256
- Plan Check / Job No.
- B21VN03091
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT PORTION OF (E) DET. GARAGE (150 SF) TO ACCESSORY DWELLING UNIT AND ADD 15'-8" x 27'-10" TO THE NEW ADU PER LAMC 12.22 A.33 (c)-(d); ALL WORK PER ENGINEERING DESIGN
- Permit Issued
- Issued on 5/18/2021
- Issuing Office
- Current Status
- CofO Issued on 1/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | SEAN SHAHMIRI |
| Corrections Issued | 3/20/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 3/24/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/18/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 5/18/2021 | SEAN SHAHMIRI |
| Issued | 5/18/2021 | APPLICANT |
| CofO in Progress | 1/20/2023 | ANTHONY EGSON |
| CofO in Progress | 1/20/2023 | ANTHONY EGSON |
| Permit Finaled | 1/25/2023 | DEROLD HAUFF |
| CofO Issued | 1/25/2023 | DEROLD HAUFF |
| Permit Finaled | 1/25/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction within easement | Cleared | 4/2/2021 | WALTER RAMIREZ |
| Address approval | Cleared | 4/12/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2021 | WALLIE JONG |
| Sewer availability | Cleared | 4/13/2021 | WALLIE JONG |
| Low Impact Development | Cleared | 4/30/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 5/3/2021 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zolfaghari,, Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/7/2021 | Conditional Approval | ALAN MORELOS |
| PLUMBING-Rough | 9/13/2021 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 10/6/2021 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 12/7/2021 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 12/7/2021 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 12/7/2021 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 12/29/2021 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 12/29/2021 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 12/29/2021 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 1/19/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2022 | Partial Approval | ANTHONY EGSON |
| HVAC-Rough | 1/19/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/31/2022 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 1/31/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 2/8/2022 | Approved | HORACE FULTZ |
| Wood Frame | 2/8/2022 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 3/10/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 3/14/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/26/2022 | Approved | ANTHONY EGSON |
| Insulation | 5/4/2022 | Approved | ANTHONY EGSON |
| Sewer | 5/4/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 5/12/2022 | No Access for Inspection | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2022 | No Access for Inspection | HORACE FULTZ |
| Green Building Rough | 5/12/2022 | No Access for Inspection | HORACE FULTZ |
| Shower Pan | 5/12/2022 | No Access for Inspection | HORACE FULTZ |
| Drywall Nailing | 5/16/2022 | Partial Approval | ANTHONY EGSON |
| Shower Pan | 5/16/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 5/27/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 5/27/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/3/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/8/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 11/8/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 11/8/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 11/8/2022 | Approved | ANTHONY EGSON |
| HVAC-Final | 11/8/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 11/8/2022 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 11/8/2022 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 11/8/2022 | Approved | ANTHONY EGSON |
| Final | 11/17/2022 | Conditional Approval | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 11/17/2022 | SGSOV Approved | ANTHONY EGSON |
| Final | 1/20/2023 | OK to Issue CofO | ANTHONY EGSON |
| Service/Power Release | 1/20/2023 | Approved | ANTHONY EGSON |